=== 2019/1/29(Tue.) === === 2019/1/30(Wed.) ===

2019/1/30(Wed.)

Weekend

Schedule

  • Current status as of 1/22: IR and Green reached X end PD.
  • 1/22 Surface inspection for PR mirrors. Cleaning will be done after 1/31.

  • 1/22 or 23 Surface inspection for SR mirrors.

  • 1/24-25 Cleaning HR of SR3, SRM.

  • 1/23 BS is aligned to Y-end PD by IR.

  • 1/24-25 ITMY is aligned to REFL by IR.

  • 1/24-25 ITMX is aligned to REFL by IR.

  • 1/24-25 Beam position of IR at SR3 is confirmed how far from the center.

  • 1/28-29 SR3 is aligned to SR2 center by IR.

  • 1/30 Green beam is injected from SR2 AR surface to Y end PD.

  • 1/31-2/1 Removing bellows at PR and SR area.
  • 1/31-2/1 Cleaning HR of PR3 and HR, AR of SR2
  • 2/4-8 Alignment of SR2 -> SRM by IR, SRM -> OMMT by IR -> OMMT -> OSTM by IR, OSTM -> OMC by IR

  • 2/4-8 Alignment of ETMY -> POS by Green

  • 2/12-15 Closing door for central area, pumping down
    • needs drift monitor for VIS

Report of work (*:responsible person)

  • COM: Green laser reached to ETMY.
  • Pedestal was replaced.
  • ISS: PD was installed on second loop.
  • CAL: Green beam monitor at ETMY will work, and needs fine alignment for finalization.
  • ETMY lock was released, but need little more time to make it work.

Work plan (*:responsible person)

  • SRM: needs some fine alignment.
  • DGS: weekly maintenance from 9am to 1pm.
  • PEM: Channel names will be replaced on Monday.
  • ETMY should be ready by the next week for Pcal finalization and ETM alignment to BS.