=== 2019/1/31(Thur.) === === Weekend === === Schedule === * Current status as of 1/22: IR and Green reached X end PD. * --(1/22: Surface inspection for PR mirrors.)-- Cleaning will be done after 1/31. * --(1/23: Surface inspection for SR mirrors.)-- * --(1/24-25: Cleaning HR of SR3, SRM.)-- * --(1/23: BS is aligned to Y-end PD by IR.)-- * --(1/27: ITMY is aligned to REFL by IR.)-- * --(1/27: ITMX is aligned to REFL by IR.)-- * --(1/27: Beam position of IR at SR3 is confirmed how far from the center.)-- * --(1/28-29: SR3 is aligned to SR2 center by IR.)-- * --(1/28: Alignment of SR2 -> SRM by IR.)-- * --(1/29: Green beam is injected from SR2 AR surface to Y end PD.)-- * 1/31: Removing bellows at PR and SR area. * 1/31-2/1: Cleaning HR of PR3 and HR, AR of SR2 * 2/4-8: SRM -> OMMT by IR -> OMMT -> OSTM by IR, OSTM -> OMC by IR * 2/4-8: Alignment of ETMY -> POS by Green * 2/12-15: Closing door for central area, pumping down * needs drift monitor for VIS ==== Report of work (*:responsible person) ==== * Type B: Height issues are being fixed now. RT model for SRs should be separated to upper slow one and lower fast one like BS. * PRM: Upgrading oplev. * IOO: High power beam shutter mirror was dropped. It will be fixed today. * ETMY: Stepping motor was not working. * AOS: heatsink for ETMX. ==== Work plan (*:responsible person) ==== * VAC: removing bellows at PR3 and SR2. * MIR: inspection and cleaning PR3 and SR2 by tomorrow.