Line 34: Line 34:
 * Report klog, and gokagra ML if urgent things.  * Please report everything you did to klog, and gokagra ML if urgent things.

2019/2/1(Fri.)

Weekend

  • Alignment work (Sat and Sun): Nakano, Enomoto, Guiguo, Wang
  • Cal: ETMY Inoue, Ohgaki
  • Miyoki

Schedule

  • Current status as of 1/22: IR and Green reached X end PD.
  • 1/22: Surface inspection for PR mirrors. Cleaning will be done after 1/31.

  • 1/23: Surface inspection for SR mirrors.

  • 1/24-25: Cleaning HR of SR3, SRM.

  • 1/23: BS is aligned to Y-end PD by IR.

  • 1/27: ITMY is aligned to REFL by IR.

  • 1/27: ITMX is aligned to REFL by IR.

  • 1/27: Beam position of IR at SR3 is confirmed how far from the center.

  • 1/28-29: SR3 is aligned to SR2 center by IR.

  • 1/28: Alignment of SR2 -> SRM by IR.

  • 1/29: Green beam is injected from SR2 AR surface to Y end PD.

  • 1/31: Removing bellows at PR and SR area.

  • 1/31-2/1: Cleaning HR of PR3 and HR, AR of SR2
  • 2/4-8: SRM -> OMMT by IR -> OMMT -> OSTM by IR, OSTM -> OMC by IR

  • 2/4-8: Alignment of ETMY -> POS by Green

  • 2/12-15: Closing door for central area, pumping down
    • needs drift monitor for VIS

Note

  • Please report everything you did to klog, and gokagra ML if urgent things.

Report of work

  • VAC: Bellows were removed at PR3 and SR2.
  • MIR: FC was put on HR of PR3 and AR of SR2.
    • FC of HR of SR will be put on today.
    • All FC will be removed today.
  • IOO: MZ was locked. we will do some measurement. Clipping was fixed.
  • Type A: ITMX is being tuned continuously.
  • PEM: ETMX fan is stopped now.
  • ETMY: we found some dust on the surface. We will talk with MIR group.

Work plan

  • High power test in the weekend
    • Laser comes to IFI with high power.
    • Laser comes to IFI today. Beam will be stopped at IMMT.
  • Type B: View port on SRM will be installed. FR of SR and some miner issues will be fixed.
    • Height change due to FC will be fixed today.

KAGRA/Commissioning/DailyWork/2019-02-01 (last edited 2019-02-01 09:29:45 by OsamuMiyakawa)