=== 2019/2/5(Tue.) === === Weekend === === Schedule === * Current status as of 1/22: IR and Green reached X end PD. * --(1/22: Surface inspection for PR mirrors.)-- Cleaning will be done after 1/31. * --(1/23: Surface inspection for SR mirrors.)-- * --(1/24-25: Cleaning HR of SR3, SRM.)-- * --(1/23: BS is aligned to Y-end PD by IR.)-- * --(1/27: ITMY is aligned to REFL by IR.)-- * --(1/27: ITMX is aligned to REFL by IR.)-- * --(1/27: Beam position of IR at SR3 is confirmed how far from the center.)-- * --(1/28-29: SR3 is aligned to SR2 center by IR.)-- * --(1/28: Alignment of SR2 -> SRM by IR.)-- * --(1/29: Green beam is injected from SR2 AR surface to Y end PD.)-- * --(1/31: Removing bellows at PR and SR area.)-- * --(1/31-2/1: Cleaning HR of PR3 and HR, AR of SR2)-- * 2/4-8: SRM -> OMMT by IR -> OMMT -> OSTM by IR, OSTM -> OMC by IR * 2/4-8: Alignment of ETMY -> POS by Green * 2/12-15: Closing door for central area, pumping down * needs drift monitor for VIS ==== Note ==== * Report klog, and gokagra ML if urgent things. ==== Report of work ==== * Type B: SRM was rotated 180degree. * SR2, SR3, SRM: Height adjustment yesterday and this morning. * SRMs model were splitter. * CAL: Injected beam to ETMY mirror and detected. * Type A: ETMY was released, Lucia will work on it. ==== Work plan ==== * COM: we will start alignment after heights of all SRMs have been aligned.