Line 4: Line 4:
 * Sat: Michimura, Enomoto, Somiya(3)
 * Sun: Enomoto, Somiya(3)
 * Mon: Enomoto, Somiya(3)

2019/2/8(Fri.)

Weekend

  • Sat: Michimura, Enomoto, Somiya(3)
  • Sun: Enomoto, Somiya(3)
  • Mon: Enomoto, Somiya(3)

Schedule

  • Current status as of 1/22: IR and Green reached X end PD.
  • 1/22: Surface inspection for PR mirrors. Cleaning will be done after 1/31.

  • 1/23: Surface inspection for SR mirrors.

  • 1/24-25: Cleaning HR of SR3, SRM.

  • 1/23: BS is aligned to Y-end PD by IR.

  • 1/27: ITMY is aligned to REFL by IR.

  • 1/27: ITMX is aligned to REFL by IR.

  • 1/27: Beam position of IR at SR3 is confirmed how far from the center.

  • 1/28-29: SR3 is aligned to SR2 center by IR.

  • 1/28: Alignment of SR2 -> SRM by IR.

  • 1/29: Green beam is injected from SR2 AR surface to Y end PD.

  • 1/31: Removing bellows at PR and SR area.

  • 1/31-2/1: Cleaning HR of PR3 and HR, AR of SR2

  • 2/5: Alignment of SRM to OMMT1 by IR

  • 2/6: Alignment of ETMY -> POS by Green

  • 2/7-8: OMMT -> OSTM by IR, OSTM -> OMC by IR

  • 2/12-15: Closing door for central area, pumping down
    • needs drift monitor for VIS

Note

  • Report all the wrok to klog, and gokagra ML if urgent things.
  • If you work other location from where it was confirmed at the morning meeting, please contact related poeple.

Report of work

  • Type B and COM: SR3 oplev loop was implemented and improved. Motion is much smaller now and it will help alignment work.
    • we saw some oscillation aound 10~Hz
  • CAM: GigE camera at POS table to see SR2.
  • AOS: TMSY got signal of green at QPD and PD.
  • FCL: temperature is between 24-25 degree. Temperature at SR2 is something strange.

Work plan

  • MIR: inspection will be done
  • AOS: Transportation of NAB in X arm from 11am.
  • AOS: We will check BS oplev coupling issue.
  • Type B: One of SRM OSEM is close to edge of range. We will fix it today.