=== 2019/2/13(Wed.) === === Weekend === === Schedule === * Current status as of 1/22: IR and Green reached X end PD. * --(1/22: Surface inspection for PR mirrors.)-- Cleaning will be done after 1/31. * --(1/23: Surface inspection for SR mirrors.)-- * --(1/24-25: Cleaning HR of SR3, SRM.)-- * --(1/23: BS is aligned to Y-end PD by IR.)-- * --(1/27: ITMY is aligned to REFL by IR.)-- * --(1/27: ITMX is aligned to REFL by IR.)-- * --(1/27: Beam position of IR at SR3 is confirmed how far from the center.)-- * --(1/28-29: SR3 is aligned to SR2 center by IR.)-- * --(1/28: Alignment of SR2 -> SRM by IR.)-- * --(1/29: Green beam is injected from SR2 AR surface to Y end PD.)-- * --(1/31: Removing bellows at PR and SR area.)-- * --(1/31-2/1: Cleaning HR of PR3 and HR, AR of SR2)-- * --(2/5: Alignment of SRM to OMMT1 by IR)-- * --(2/6: Alignment of ETMY -> POS by Green)-- * 2/7-8: OMMT -> OSTM by IR, OSTM -> OMC by IR * 2/12-15: Closing door for central area, pumping down * needs drift monitor for VIS ==== Note ==== ==== Report of work ==== * ETMY: we found that key stop was touching somewhere and fixed it. This is for vertical. * we will check LVDT of IP and horizontal motion * ETMX: Buffle of NAB at EXA chamber was installed. PD will be installed on baffle. ==== Work plan ==== *