=== 2019/2/21(Wed.) === === Weekend === === Schedule === * Yend * --(1/25-2/20: Yend Pcal finalization)-- * 2/25-3/4: Yend WAB * 3/6~ : Yend pumpdown 3/6~ * 3/7,8: leak test * Xend * --(2/11-2/14: Xend NAB installation)-- * 2/21: Removing FC, Payload release * 2/23-3/10: Xend Pcal finalization 1 * Periscope installation * Beam position by IR and Green * 2/27: ETMX release * 3/5: ETMX aligned * 3/5-3/10: Xend Pcal finalization 2 * 3/11,12 Xend WAB finalization * 3/19,20, Heatlink etc. * 3/22 Pumping down * Leak test * 3/11~ : Night work start * 2/18-3/22 DRMI commissioning * 3/11-4/5 Y arm commissioning * 3/25-4/5 FPMI commissioning ==== Note ==== ==== Report of work ==== * COM: Alingnment for PR and BS and ITMS were recovered, and Michelson fringe was seen! * SRM: Yaw drift exists. * SR2: oplev shows something hitting. * VAC: small leakage was found at ITMY, but we leave it. * PEM: Camera lens of ITM is not enough. * DGS: PC for ETMX and ETMY were replaced. ==== Work plan ==== * ETMX: Removing FC afternoon.