=== 2019/2/27(Wed.) === === Schedule === * Center * 2/26-27: Venting * 2/27: Fixing PRM and PR3 * 3/4-5: Re-alignment * 3/5-6: Closing * Yend * --(1/25-2/20: Yend Pcal finalization)-- * 2/25-3/4: Yend WAB finalization * 3/5-6: Closing * 3/6~ : Yend pumpdown 3/6~ * 3/7,8: leak test * Xend * --(2/11-2/14: Xend NAB installation)-- * --(2/21: Removing FC, Payload release)-- * 2/23-3/10: Xend Pcal finalization 1 * Periscope installation * Beam position by IR and Green * 2/27: ETMX release * 3/5: ETMX aligned * 3/5-3/10: Xend Pcal finalization 2 * 3/11,12 Xend WAB finalization * 3/19,20, Heatlink etc. * 3/22 Pumping down * Leak test * 3/11~ : Night work starts * 2/18-3/22 DRMI commissioning * 3/11-4/5 Y arm commissioning * 3/25-4/5 FPMI commissioning ==== Note ==== === Weekend === ==== Report of work ==== * Type A: Measurements TF for ITMX and ITMY are going on yesterday and today. * Type B: Monitoring SRMs for venting. Lucia, Enzo, and Fabian will look after. * WAB finalization at ETMY is almost done, at the nominal position. * CRY: sensors are monitored on payload. It is ready for cooling. ==== Work plan ==== * PEM: IMC cover will be put. * DGS: replacing RTPC for BS and severals if we have enough time. * COM: Alignment of central area on Monday and Tuesday.