=== 2019/2/28(Thur.) ===

=== Schedule ===
 * Center
  * --(2/26-27: Venting)--
  * 2/28: Fixing PRM, PR3 and SRM
  * 2/29-5: Re-alignment
  * 3/5-6: Closing

 * Yend
  * --(1/25-2/20: Yend Pcal finalization)-- 
  * 2/25-3/4: Yend WAB finalization
  * 3/5-6: Closing
  * 3/6~ : Yend pumpdown 3/6~
   * 3/7,8: leak test 

 * Xend
  * --(2/11-2/14: Xend NAB installation)--
  * --(2/21: Removing FC, Payload release)--
  * 2/23-3/10: Xend Pcal finalization 1
   * Periscope installation
   * Beam position by IR and Green
  * 2/27: ETMX release
  * 3/5: ETMX aligned
  * 3/5-3/10: Xend Pcal finalization 2
  * 3/11,12 Xend WAB finalization
  * 3/19,20, Heatlink etc.
  * 3/22 Pumping down
   * Leak test
 
 * 3/11~ : Night work starts

 * 2/18-3/22 DRMI commissioning
 * 3/11-4/5 Y arm commissioning
 * 3/25-4/5 FPMI commissioning

==== Note ====
 * Takoyaki party at 6pm.


=== Weekend ===

==== Report of work ====

 * PRM: Vibration measurement of cooler.
 * DGS: replaced RTPC of BS to V4 and PRM to V3.

==== Work plan ====

 * VIS: Fixing PRM, PR3 and SRM
 * COM: Alignment of central area after tomorrow.