=== 2019/3/5(Tue.) === === Schedule === * Center * --(2/26-27: Venting)-- * 2/28-3/6: Health check and maintenance for VIS * --(PRM: One flag was dropped. -> leave it)-- * PRM: Misalignment does not reach where beam hits damper. -> 3/4-6 * --(3/5 PR3: range -> incline by 20-30mrad at mirror because of bistable. -> 3/5)-- * BS: Yaw offset adjustment by hand. -> 3/5-6 * 3/2-6: Re-alignment * 3/5 afternoon or 3/6 morning: Coolers for ITMs will be stopped for 2-3 hours to change water. * 3/7: Closing * 3/8: pump down * Yend * --(1/25-2/20: Yend Pcal finalization)-- * --(3/5: EYA remaining works by Enomoto, Inoue.)-- * 2/25-3/4: Yend WAB finalization * 3/5: AOS EY and EX(if they have time) work. * 3/6: Y end closing (no laser hazard at least in the morning) * Alignment to ETMX by 3/7 morning * 3/7: Y end pump down * 3/7,8: leak test * Xend * --(2/11-2/14: Xend NAB installation)-- * --(2/21: Removing FC, Payload release)-- * --(2/27: ETMX release)-- * 2/23-3/6: Xend Pcal finalization 1 * --(Periscope installation)-- * Beam position by IR and Green * 3/5 and 3/11~: ETMX seems to be hitting somewhere? Tuning was not enough(by Takahashi). * 3/6: ETMX aligned with oplev accuracy * 3/5: AOS EY and EX(if they have time) work. * 3/6: Green X alignment (no IR), and no hazard at Y end. * 3/9-10(fastest, then 3/23): Pcal finalization * 3/11, 18,19: Xend WAB finalization. * 3/19: Heatlink etc. * 3/19: ETMX finalization by Takahashi * 3/21 closing * 3/22 Pumping down * Leak test * 3/11~ : Night work starts, daily meeting will be moved to 1PM * Summary of work will last for a while in the morning meeting. * 2/18-3/22 DRMI commissioning * 3/11-4/5 Y arm commissioning * 3/25-4/5 FPMI commissioning ==== Note ==== === Weekend === ==== Report of work ==== * Type B: Fixed tilt and adjusted OSEMs. TF shows that PR3 seems to be healthy now. * Green beam reached ETMX * PRM was touching at several places. Needs to measure TF again. * BS: Manual adjustment for yaw was done. Pitch offset has big offset and probably Oplev may be no reference anymore. Needs alignment to ETMY. * Pcal: ETMY was done. ETMX will be done today. * ETMX: no touching was found, but some of upper stage did not move. It seems to be possible to align. ==== Work plan ==== * IOO: Yamako-kun will do noise hunting work on MZ. Needs alignment for iMC for alignment to ETMY. * VAC: cleaning at ETMY.