=== 2019/3/15(Fri.) === === Schedule === * Center * --(2/26-27: Venting)-- * 2/28-3/15: Health check and maintenance for VIS * --(PRM: One flag was dropped. -> leave it)-- * --(3/4-14 PRM: Misalignment does not reach where beam hits damper.)-- * --(3/6 PR3: range -> incline by 20-30mrad at mirror because of bistable.)-- * --(3/15: BS: Yaw offset adjustment by hand. -> 3/5-6)-- * --(3/12: BS ok)-- * 3/15: some SRs work * --(3/5 afternoon or 3/6 morning: Coolers for ITMs will be stopped for 2-3 hours to change water.)-- * 3/18-19: Re-alignment * 3/19: Closing * 3/20: pump down * Yend * --(1/25-2/20: Yend Pcal finalization)-- * --(3/5: EYA remaining works by Enomoto, Inoue.)-- * --(2/25-3/5: Yend WAB finalization)-- * --(3/6: Y end closing (no laser hazard at least in the morning))-- * --(3/7: Y end pump down)-- * --(3/7,8: leak test)-- * Xend * --(2/11-2/14: Xend NAB installation)-- * --(2/21: Removing FC, Payload release)-- * --(2/27: ETMX release)-- * --(2/23-3/6: Xend Pcal finalization 1)-- * --(Periscope installation)-- * --(3/6: Beam position by IR and Green)-- * --(3/5 AOS: EY and EX(if they have time) work.)-- * --(3/6: Green X alignment (no IR), and no hazard at Y end.)-- * 3/11, 18,19: Xend WAB finalization. * 3/11~3/15: ETMX tuning. * 3/19: Heatlink etc. * 3/19: ETMX finalization by Takahashi * 3/18,19: ETMX alignement * 3/21 closing * 3/22 Pumping down * Leak test * 3/18~ : Night work starts, daily meeting will be moved to 1PM * Summary of work will last for a while in the morning meeting. * 2/18-2/22: PRMI commissioning * 3/25~?: DRMI commissioning * 3/25-4/19: Y arm commissioning * 3/25-4/19: FPMI commissioning ==== Note ==== * Night work does not start from 3/11 due to the 2weeks delay by VIS troubles. * It does not mean that night work is prohibited but it means that officially night shift responsible person won't be assigned and we have no daily meeting at 1pm. * Official night work starts 3/18 or 3/25, but not determined yet. === Weekend === ==== Report of work ==== * Type B: One of SR2 OSEM output was 30% higher, it will be compensated. * Need some work for BS and SR2. * Type Bp: PRM still has small peak but all other looks fine. * Type A: ETMX was sitting at the cryopayload. It was turned out ~10mm lower. * We will lift up ~5mm today. * Maybe Pcal needs alignment again. * MIF: Green source for Y was replaced yesterday. * Green laser is ready for alignment. ==== Work plan ==== * ETMY: f3 is stuck. Sensitivity will be calculated again with current VIS situation. * Dolphin connection to k1omc is planned during lunch time.