2019/4/2(Tue.)
Schedule
- Center
3/25: Venting
- 3/27-4/10: Fixing PR2
- 4/12: Closing and pump down
- ITMX:
3/19: Cooling stop
3/25: Venting start
3/27: Opning chamber
- 3/27~: Fixing thermal touch
- ~4/4: closing chamber and start pumping down.
- 4/12: Cooling starts.
- Xend
3/25: closing and pump down
- 4/12: Cooling start
- Yend
3/26: Venting start
3/28~: Fixing short inside chamber
- ~4/3: closing chamber and start pumping down.
- 4/10: Cooling starts.
- 4/8~ or 4/15~: Night work starts, daily meeting will be moved to 1PM
- Summary of work will last for a while in the morning meeting.
- End of April~: DRMI commissioning
- End of April~: Y arm commissioning
- ~End of May: FPMI commissioning
Note
- Official night work starts 4/8 or 4/15.
Weekend
Report of work
- CRY: One of the refrigerator on ITMY was reset(tuned off and turned on), then temperature started going low.
- One more refrigerator will be reset today.