Line 47: Line 47:

 * DGS: maintenance; replacing PCs(k1als, k1lsc, k1imc0, k1srm) and exchanging AC100V power at rack for k1gate

2019/4/3(Wed.)

Schedule

  • Center
    • 3/25: Venting

    • 3/27-4/10: Fixing PR2
    • 4/12: Closing and pump down
  • ITMX:
    • 3/19: Cooling stop

    • 3/25: Venting start

    • 3/27: Opning chamber

    • 3/27~: Fixing thermal touch

    • 4/2~: closing chamber and start pumping down.
    • 4/12: Cooling starts.
  • Xend
    • 3/25: closing and pump down

    • 4/11: Cooling start
  • Yend
    • 3/26: Venting start

    • 3/28~: Fixing short inside chamber

    • 4/5~: closing chamber and start pumping down.
    • 4/9: Cooling starts.
  • 4/8~ or 4/15~ : Night work starts, daily meeting will be moved to 1PM
    • Summary of work will last for a while in the morning meeting.
  • End of April~: DRMI commissioning
  • End of April~: Y arm commissioning
  • ~End of May: FPMI commissioning

Note

  • Official night work starts 4/8 or 4/15.

Weekend

Report of work

  • Type A: ETMY actuator was not working. Fix it today, close chamber tomorrow.
  • Type A: Opleb of ITMY was recovered. Wind shield was dropped off by loose tape.
  • MIF: Green laser for Yarm was opened somehow.

Work plan

  • DGS: maintenance; replacing PCs(k1als, k1lsc, k1imc0, k1srm) and exchanging AC100V power at rack for k1gate