=== 2019/4/3(Wed.) === ==== Schedule ==== * Center * --(3/25: Venting)-- * 3/27-4/10: Fixing PR2 * 4/12: Closing and pump down * ITMX: * --(3/19: Cooling stop)-- * --(3/25: Venting start)-- * --(3/27: Opning chamber)-- * --(3/27~: Fixing thermal touch)-- * 4/2~: closing chamber and start pumping down. * 4/12: Cooling starts. * Xend * --(3/25: closing and pump down)-- * 4/11: Cooling start * Yend * --(3/26: Venting start)-- * --(3/28~: Fixing short inside chamber)-- * 4/5~: closing chamber and start pumping down. * 4/9: Cooling starts. * 4/8~ or 4/15~ : Night work starts, daily meeting will be moved to 1PM * Summary of work will last for a while in the morning meeting. * End of April~: DRMI commissioning * End of April~: Y arm commissioning * ~End of May: FPMI commissioning ==== Note ==== * Official night work starts 4/8 or 4/15. ==== Weekend ==== * ==== Report of work ==== * Type A: ETMY actuator was not working. Fix it today, close chamber tomorrow. * Type A: Opleb of ITMY was recovered. Wind shield was dropped off by loose tape. * MIF: Green laser for Yarm was opened somehow. ==== Work plan ==== * DGS: maintenance; replacing PCs(k1als, k1lsc, k1imc0, k1srm) and exchanging AC100V power at rack for k1gate