=== 2019/4/9(Tue.) ===

==== Schedule ====
 * Center
  * --(3/25: Venting)--
  * 3/27-4/9: Fixing PR2
   * --(4/4 -4/5: Gluing)--
   * 4/8: alignment check
   * 4/8-9: OSEM adjustment
  * 4/10-11: Closing
  * 4/12: Pump down
  * 4/15~: Leak check

 * ITMX: 
  * --(3/19: Cooling stop)--
  * --(3/25: Venting start)--
  * --(3/27: Opning chamber)--
  * --(3/27~: Fixing thermal touch)--
  * --(4/2~: closing chamber and start pumping down)--
  * 4/12: Cooling starts.

 * Xend
  * --(3/25: closing and pump down)--
  * 4/8: Leak check
  * 4/9-10: venting
  * 4/11: Exchange a broken LED for Photo sensor
  * 4/12: closing chamber and start pumping down
  * 4/15: Leak check
  * 4/19(or 22): Cooling start

 * Yend
  * --(3/26: Venting start)--
  * --(3/28~: Fixing short inside chamber)--
  * --(4/3: Fixing F0 actuator)--
  * --(4/4~: closing chamber and start pumping down.)--
  * 4/12: Cooling starts.


 * 4/8: Daily meeting will be moved to 1PM
  * Summary of work will last for a while in the morning meeting.

 * April: Measurement of TF, payload diagonalization on ITMX
 * End of April~: DRMI commissioning
 * End of April~: Y arm commissioning
 * ~End of May: FPMI commissioning

==== Note ====
  * Commissioning meeting moves at 1PM from today.

==== Night work ====
 * IOO: iMC alignment (Kokeyama, Guiguo, June-gyu)

==== Weekend ====
 *
 
==== Report of work ====
 * MIF: Alignment was done yesterday.
 * PEM, VAC: VAC monitor has been almost implemented.



==== Work plan ====
 * Type B: OSEMs for PRM, PR2, SR2, BS should be adjusted today, and probably tomorrow.
 * VIS: Health check.
 * Type A: Venting ETMX is planned today, and LED will be exchanged on Thursday.
 * IOO: night work for iMC alignment.