=== 2019/4/11(Thur.) === ==== Schedule ==== * Center * --(3/25: Venting)-- * --(3/27-4/9: Fixing PR2 or others)-- * --(4/4 -4/5: Gluing)-- * --(4/8: alignment check)-- * --(4/8-10: OSEM adjustment)-- * --(4/10: alignment check)-- * 4/11: VIS final health check * 4/11-12: Closing * 4/12: Pump down * 4/15~: Leak check * ITMX: * --(3/19: Cooling stop)-- * --(3/25: Venting start)-- * --(3/27: Opning chamber)-- * --(3/27~: Fixing thermal touch)-- * --(4/2~: closing chamber and start pumping down)-- * --(4/11: Cooling starts.)-- * Xend * --(3/25: closing and pump down)-- * --(4/8: Leak check)-- * --(4/9-10: venting)-- * 4/11: Exchange a broken LED for Photo sensor * 4/12: closing chamber and start pumping down * 4/15: Leak check * 4/19(or 22): Cooling start * Yend * --(3/26: Venting start)-- * --(3/28~: Fixing short inside chamber)-- * --(4/3: Fixing F0 actuator)-- * --(4/4~: closing chamber and start pumping down.)-- * --(4/11: Cooling starts.)-- * April: Measurement of TF, payload diagonalization on ITMX * End of April~: DRMI commissioning * End of April~: Y arm commissioning * ~End of May: FPMI commissioning ==== Note ==== * Commissioning meeting moves at 1PM from this week. ==== Night work ==== * IOO: iMC alignment (Kokeyama, Guiguo, June-gyu) ==== Weekend ==== * Weekend work at the control room: Fabian for monitor, Lucia for monitor and control. ==== Report of work ==== * Type B: OSEM adjustments for SR2 and PR2 were done. * SR2 pitch had big offset. * Type B: Offset for IP of BS was removed. * Top cover was removed. * MIF: The final alignment check was done last night. ==== Work plan ==== * VIS: Health check for all VIS in the central part today. * PR3 was checked and it was confirmed healthy. * All VIS in the center area seems to be healthy. * CRY: A LED for PD sensor ETMX will be replaced. * VIS: Monitor for ITMX and ETMY will be by Lucia. * Monitor for center tomorrow will be by Fabian, Okutomi. * CRY: cryo payload should be monitored by BF for pitch, XX for vertical by Ushiba with VIS team. * LED was fixed in the morning by Ushiba-kun. * Weekend work at the control room: Fabian for monitor, Lucia for monitor and control.