Differences between revisions 2 and 3
Revision 2 as of 2019-04-12 11:27:43
Size: 2144
Comment:
Revision 3 as of 2019-04-12 13:04:48
Size: 2381
Comment:
Deletions are marked like this. Additions are marked like this.
Line 22: Line 22:
  * --(4/11: Cooling starts.)--   * --(4/10: Cooling starts.)--
Line 29: Line 29:
  * 4/13: closing chamber and start pumping down
  * 4/22: Leak check
  * 4/12: closing chamber and start pumping down
  * 4/15: Leak check
Line 38: Line 38:
  * --(4/11: Cooling starts.)--   * --(4/10: Cooling starts.)--
Line 65: Line 65:
  * Pumping down at ETMX was postponed tomorrow because health check was performed with wrong mirror position.
  * Pumping down at center was postponed around 3pm because health check of SRM needs a little more time due to a tripping.

2019/4/12(Fri.)

Schedule

  • Center
    • 3/25: Venting

    • 3/27-4/9: Fixing PR2 or others

      • 4/4 -4/5: Gluing

      • 4/8: alignment check

      • 4/8-10: OSEM adjustment

    • 4/10: alignment check

    • 4/11: VIS final health check
    • 4/11-12: Closing
    • 4/12: Pump down
    • 4/15~: Leak check
  • ITMX:
    • 3/19: Cooling stop

    • 3/25: Venting start

    • 3/27: Opning chamber

    • 3/27~: Fixing thermal touch

    • 4/2~: closing chamber and start pumping down

    • 4/10: Cooling starts.

  • Xend
    • 3/25: closing and pump down

    • 4/8: Leak check

    • 4/9-10: venting

    • 4/11: Exchange a broken LED for Photo sensor

    • 4/12: closing chamber and start pumping down
    • 4/15: Leak check
    • 4/22: Cooling start
  • Yend
    • 3/26: Venting start

    • 3/28~: Fixing short inside chamber

    • 4/3: Fixing F0 actuator

    • 4/4~: closing chamber and start pumping down.

    • 4/10: Cooling starts.

  • April: Measurement of TF, payload diagonalization on ITMX
  • End of April~: DRMI commissioning
  • End of April~: Y arm commissioning
  • ~End of May: FPMI commissioning

Note

  • Commissioning meeting moves at 1PM from this week.

Night work

  • IOO: iMC alignment (Kokeyama, Guiguo, June-gyu)

Weekend

  • Weekend work at the control room: Fabian for monitor, Lucia for monitor and control.
  • PEM(Sat.): Checking PEMs by Yokozawa, Washimi, Tanaka
  • VAC(Sat.): Kimura, Saito, Mirapro

Report of work

  • CRY: ETMX PD LED was exchanged by Ushiba-kun.
  • Type A: It was reported that Lucia checked ETMX was healthy.

Work plan

  • MIF: Control loop for all VIS in the central are will be engaged this morning. It should be checked conflicting for other work; VIS, VAC.
  • Type B: Only SRM should be checked this morning. Fabian will do.
  • VIS: Monitor for ETMX and center area during pumping down will be by Fabian.
    • Pumping down at ETMX was postponed tomorrow because health check was performed with wrong mirror position.
    • Pumping down at center was postponed around 3pm because health check of SRM needs a little more time due to a tripping.
  • Weekend work at the control room: Fabian for monitor, Lucia for monitor and control.

KAGRA/Commissioning/DailyWork/2019-04-12 (last edited 2019-04-12 13:04:48 by OsamuMiyakawa)