=== 2019/4/12(Fri.) === ==== Schedule ==== * Center * --(3/25: Venting)-- * --(3/27-4/9: Fixing PR2 or others)-- * --(4/4 -4/5: Gluing)-- * --(4/8: alignment check)-- * --(4/8-10: OSEM adjustment)-- * --(4/10: alignment check)-- * 4/11: VIS final health check * 4/11-12: Closing * 4/12: Pump down * 4/15~: Leak check * ITMX: * --(3/19: Cooling stop)-- * --(3/25: Venting start)-- * --(3/27: Opning chamber)-- * --(3/27~: Fixing thermal touch)-- * --(4/2~: closing chamber and start pumping down)-- * --(4/10: Cooling starts.)-- * Xend * --(3/25: closing and pump down)-- * --(4/8: Leak check)-- * --(4/9-10: venting)-- * --(4/11: Exchange a broken LED for Photo sensor)-- * 4/12: closing chamber and start pumping down * 4/15: Leak check * 4/22: Cooling start * Yend * --(3/26: Venting start)-- * --(3/28~: Fixing short inside chamber)-- * --(4/3: Fixing F0 actuator)-- * --(4/4~: closing chamber and start pumping down.)-- * --(4/10: Cooling starts.)-- * April: Measurement of TF, payload diagonalization on ITMX * End of April~: DRMI commissioning * End of April~: Y arm commissioning * ~End of May: FPMI commissioning ==== Note ==== * Commissioning meeting moves at 1PM from this week. ==== Night work ==== * IOO: iMC alignment (Kokeyama, Guiguo, June-gyu) ==== Weekend ==== * Weekend work at the control room: Fabian for monitor, Lucia for monitor and control. * PEM(Sat.): Checking PEMs by Yokozawa, Washimi, Tanaka * VAC(Sat.): Kimura, Saito, Mirapro ==== Report of work ==== * CRY: ETMX PD LED was exchanged by Ushiba-kun. * Type A: It was reported that Lucia checked ETMX was healthy. ==== Work plan ==== * MIF: Control loop for all VIS in the central are will be engaged this morning. It should be checked conflicting for other work; VIS, VAC. * Type B: Only SRM should be checked this morning. Fabian will do. * VIS: Monitor for ETMX and center area during pumping down will be by Fabian. * Pumping down at ETMX was postponed tomorrow because health check was performed with wrong mirror position. * Pumping down at center was postponed around 3pm because health check of SRM needs a little more time due to a tripping. * Weekend work at the control room: Fabian for monitor, Lucia for monitor and control.