=== 2019/4/24(Wed.) === ==== Schedule ==== * Center * --(3/25: Venting)-- * --(3/27-4/9: Fixing PR2 or others)-- * --(4/4 -4/5: Gluing)-- * --(4/8: alignment check)-- * --(4/8-10: OSEM adjustment)-- * --(4/10: alignment check)-- * --(4/11: VIS final health check)-- * --(4/11-12: Closing)-- * --(4/12: Pump down)-- * 4/29,30: Leak check * ITMX: * --(3/19: Cooling stop)-- * --(3/25: Venting start)-- * --(3/27: Opning chamber)-- * --(3/27~: Fixing thermal touch)-- * --(4/2~: closing chamber and start pumping down)-- * --(4/10: Cooling starts.)-- * Xend * --(3/25: closing and pump down)-- * --(4/8: Leak check)-- * --(4/9-10: venting)-- * --(4/11: Exchange a broken LED for Photo sensor)-- * --(4/12: closing chamber and start pumping down)-- * --(4/22: Leak check)-- * --(4/22: vent)-- * 4/24: fix oplev mirror * 4/25: Pumpdown * 5/2: leak check * 5/2: Cooling start * Yend * --(3/26: Venting start)-- * --(3/28~: Fixing short inside chamber)-- * --(4/3: Fixing F0 actuator)-- * --(4/4~: closing chamber and start pumping down.)-- * --(4/10: Cooling starts.)-- * April: Measurement of TF, payload diagonalization on ITMX * End of April~: DRMI commissioning * End of April~: Y arm commissioning * ~End of May: FPMI commissioning ==== Note ==== * 1pm commissioning meeting will start again. ==== Night work ==== * ==== Weekend ==== * ==== Report of work ==== * ITMY: L was excited but TM actuator did not work. It will be checked today. * Type B: ezca commands did not work by some environmental issue, probably related to python compatibility. Mark found some way to fix the issue. It will be documented. ==== Work plan ==== * iMC work in the afternoon. * Yarm commissioning work after 5pm. * Maintenance is planed today. * Replacing k1als0 and other PC. * Replacing HDD of k1nfs0. It takes 10-20min but all desktop will be stopped.