Line 1: Line 1:
=== 2019/4/24(Wed.) === === 2019/4/25(Thur.) ===
Line 31: Line 31:
  * --(4/22: vent)-
  * 4/24: fix oplev mirror
  * --(4/22: vent)--
  * --(4/24: fix oplev mirror)--
Line 59: Line 59:
 * ITMY: L was excited but TM actuator did not work. It will be checked today.
 * Type B: ezca commands did not work by some environmental issue, probably related to python compatibility. Mark found some way to fix the issue. It will be documented.
 * ETMX: Oplev mirror at IM was fixed.
 * ETMX: Opened hatch and checked the cable. Coupling at tower part still exists. It could be cable swapping.

 * ITMY: Accelerometer was fixed.
 * ITMY: IM actuator did not work. MN will be used for hierarchy control.
  * TM actuator had a problem on the circuit. Mechanically it seems to be OK.

 * VAC: Cleaning at ETMX is going on.

 * Maintenance was done.
  * Replaced k1als0 and k1lsc0.
  * Replaced HDD of k1nfs0.
Line 63: Line 73:
 * iMC work in the afternoon.
 * Yarm commissioning work after 5pm.
 * Maintenance is planed today.
  * Replacing k1als0 and other PC.
  * Replacing HDD of k1nfs0. It takes 10-20min but all desktop will be stopped.
 * IOO: Works for shutter this afternoon.

2019/4/25(Thur.)

Schedule

  • Center
    • 3/25: Venting

    • 3/27-4/9: Fixing PR2 or others

      • 4/4 -4/5: Gluing

      • 4/8: alignment check

      • 4/8-10: OSEM adjustment

    • 4/10: alignment check

    • 4/11: VIS final health check

    • 4/11-12: Closing

    • 4/12: Pump down

    • 4/29,30: Leak check
  • ITMX:
    • 3/19: Cooling stop

    • 3/25: Venting start

    • 3/27: Opning chamber

    • 3/27~: Fixing thermal touch

    • 4/2~: closing chamber and start pumping down

    • 4/10: Cooling starts.

  • Xend
    • 3/25: closing and pump down

    • 4/8: Leak check

    • 4/9-10: venting

    • 4/11: Exchange a broken LED for Photo sensor

    • 4/12: closing chamber and start pumping down

    • 4/22: Leak check

    • 4/22: vent

    • 4/24: fix oplev mirror

    • 4/25: Pumpdown
    • 5/2: leak check
    • 5/2: Cooling start
  • Yend
    • 3/26: Venting start

    • 3/28~: Fixing short inside chamber

    • 4/3: Fixing F0 actuator

    • 4/4~: closing chamber and start pumping down.

    • 4/10: Cooling starts.

  • April: Measurement of TF, payload diagonalization on ITMX
  • End of April~: DRMI commissioning
  • End of April~: Y arm commissioning
  • ~End of May: FPMI commissioning

Note

  • 1pm commissioning meeting will start again.

Night work

Weekend

Report of work

  • ETMX: Oplev mirror at IM was fixed.
  • ETMX: Opened hatch and checked the cable. Coupling at tower part still exists. It could be cable swapping.
  • ITMY: Accelerometer was fixed.
  • ITMY: IM actuator did not work. MN will be used for hierarchy control.
    • TM actuator had a problem on the circuit. Mechanically it seems to be OK.
  • VAC: Cleaning at ETMX is going on.
  • Maintenance was done.
    • Replaced k1als0 and k1lsc0.
    • Replaced HDD of k1nfs0.

Work plan

  • IOO: Works for shutter this afternoon.

KAGRA/Commissioning/DailyWork/2019-04-25 (last edited 2019-04-25 13:05:20 by OsamuMiyakawa)