=== 2019/4/25(Thur.) === ==== Schedule ==== * Center * --(3/25: Venting)-- * --(3/27-4/9: Fixing PR2 or others)-- * --(4/4 -4/5: Gluing)-- * --(4/8: alignment check)-- * --(4/8-10: OSEM adjustment)-- * --(4/10: alignment check)-- * --(4/11: VIS final health check)-- * --(4/11-12: Closing)-- * --(4/12: Pump down)-- * 4/29,30: Leak check * ITMX: * --(3/19: Cooling stop)-- * --(3/25: Venting start)-- * --(3/27: Opning chamber)-- * --(3/27~: Fixing thermal touch)-- * --(4/2~: closing chamber and start pumping down)-- * --(4/10: Cooling starts.)-- * Xend * --(3/25: closing and pump down)-- * --(4/8: Leak check)-- * --(4/9-10: venting)-- * --(4/11: Exchange a broken LED for Photo sensor)-- * --(4/12: closing chamber and start pumping down)-- * --(4/22: Leak check)-- * --(4/22: vent)-- * --(4/24: fix oplev mirror)-- * --(4/25: Pumpdown)-- * 5/2: leak check * 5/2: Cooling start * Yend * --(3/26: Venting start)-- * --(3/28~: Fixing short inside chamber)-- * --(4/3: Fixing F0 actuator)-- * --(4/4~: closing chamber and start pumping down.)-- * --(4/10: Cooling starts.)-- * April: Measurement of TF, payload diagonalization on ITMX * End of April~: DRMI commissioning * End of April~: Y arm commissioning * ~End of May: FPMI commissioning ==== Note ==== * ==== Night work ==== * Y arm commissioning, from the control room. ==== Weekend ==== * Big holiday will start tomorrow. * CAL: 4/27 Yokozawa, Washimi in the mine. * Other work specially IFO work remotely from the control room will be proceeded: ==== Report of work ==== * VAC: pumping down at ETMX started. -> monitor: Okutomi * Measured TF each point to L using IFO with green light. * Diagnalization of test mass will be going on. * Measurement for phase lock loop of Y arm will done by Sugimoto-kun, Enomoto-kun. * IOO: started the second loop ISS by Kuromiya-kun and Nakano-kun. ==== Work plan ==== * Type B: continuously improving Gardian code.