=== 2019/5/14(Tue.) === ==== Schedule ==== * 5/14: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (BS, ) * 5/20-24: Exchanging cryo valves. * Center * --(4/12: Pump down)-- * --(4/29,30: Leak check)-- * --(~5/3: Vent and pumpdown)-- * --(5/9: leak check)-- * ITMX: * --(4/2~: closing chamber and start pumping down.)-- * --(4/10: Cooling starts.)-- * --(5/8: Cooling done)-- * Xend * --(4/25: Pumpdown)-- * --(5/2: leak check)-- * --(5/2: Cooling start)-- * Yend * --(4/4~: closing chamber and start pumping down.)-- * --(4/10: Cooling starts.)-- * --(5/8: Cooling done)-- * April: Measurement of TF, payload diagonalization on ITMX * End of April~: Y arm commissioning * ~End of May: FPMI commissioning ==== Note ==== * ==== Night work ==== ==== Weekend ==== ==== Report of work ==== * Height adsustment: Target is ITMY 6mm upper, ITMX 5mm lower. * One of the stepping motor did not work. It will be checked today. * ITMY adjustment was done. ITMX height changed ~2mm. * ETMY cables to coil was checked. It was found that One of the pair was flipped, and they were swapped. * COM: After hight adjustment, IFO will be aligned again. Some lock acquisition will be tried again. * DGS: Maintenance will be planned for adding cards to k1omc. -> go to the safe mode for all the dolphin connected VIS. * In the next week, several other PCs(LSC, ASC, ALS) will have more cards. ==== Work plan ====