=== 2019/5/22(Wed.) === ==== Schedule ==== * 5/14: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (BS, ) * 5/20-24: Exchanging cryo valves. * 6/8: Engineering run * ITMX * 5/22AM~: tuned off cryostat cooler, finesse measurement for Xarm * ETMX * --(5/2: Cooling start)-- * 5/29: Cooling done * ITMY * 5/23AM~: tuned off cryostat cooler, finesse measurement for Yarm * ETMY * 5/17~: tuned off ETMY cryostat cooler * 5/24PM~ inject 100Pa Nitrogen. * 5/27 evacuation of Nitrogen. * 6/3-6/14: Installation of TMS for ETMY * 4/22-5/31: Yarm commissioning * 5/27-6/30: DRMI commissioning * 7/1-8/9: DRFPMI commissioning * 8/12-10/4: DRFPMI ASC * 10/7-11/15: Post Commissioning * 11/18-12/13: Noise hunting ==== Note ==== * There was request to CRY people to attend the morning or noon meeting. * CRY: Exchanging cryo valve during this week. ==== Night work ==== ==== Weekend ==== ==== Report of work ==== * COM: It was found that calculation of finesse estimation from ring down measurement was wrong. It was actually Xarm ~1450(close to design value), Yarm ~440(1/3 of design value). * Type Bp: Satellite box for PR2 was replaced. One new box was no signal at one of the channels. It was replaced to other new one and it worked. ==== Work plan ==== * CRY: ITMX cryostat cooler will be stopped. * IOO: MZ will be released today from the main path of PSL. * DGS: Maintenance work for adding BIO cards. * DGS: Camera server maintenance. If you need camera, please use k1cam1.