=== 2019/5/24(Fri.) === ==== Schedule ==== * --(5/22: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (BS) )-- * --(5/22-23: MZ release from PSL)-- * --(5/20-24: Exchanging cryo valves.)-- * 5/27-6/2: Y arm mass lock. * 6/3-6/14: Installation of TMS for ETMY * 6/8: Engineering run * ITMX * --(5/22AM~: tuned off cryostat cooler, finesse measurement for Xarm)-- * --(5/22AM~: tuned off shield cooler, finesse measurement for Xarm)-- * ETMX * --(5/2: Cooling start)-- * 5/29: Cooling done * ITMY * --(5/23AM~: tuned off cryostat cooler, finesse measurement for Yarm)-- * ETMY * --(5/17~: tuned off ETMY cryostat cooler)-- * 5/24PM~ inject 100Pa Nitrogen. -> postponed after 6/3? * 5/27 evacuation of Nitrogen. -> postponed after 6/3? * Long term: * 4/22-5/31: Yarm commissioning * 5/27-6/30: DRMI commissioning * 7/1-8/9: DRFPMI commissioning * 8/12-10/4: DRFPMI ASC * 10/7-11/15: Post Commissioning * 11/18-12/13: Noise hunting ==== Note ==== ==== Night work ==== ==== Weekend ==== * IOO maybe ==== Report of work ==== * COM: Finesse measurement did not succeed by some troubles. * T cam fo X arm had trouble. It was fixed this morning by restarting Team. * SR3 drift caused by VIS work in the mid night. Working time should be coordinated. * Type A: After stopping cryo cooler of ITMY stopped and temperature went up, ITMY surface looks better by T cam image with green light. Spots by dust? seems to be gone and the surface looks more clean. * IOO: Alignment of PSL is back after MZ was removed day before yesterday. ==== Work plan ==== * DGS: Maintenance work afternoon for k1asc0.