Line 4: Line 4:
 * --(5/22: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (BS) )--
Line 8: Line 7:
 * 5/29: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (specially BS)
Line 17: Line 17:
  * 5/29: Cooling done
Line 32: Line 31:

2019/5/28(Tue.)

Schedule

  • 5/22-23: MZ release from PSL

  • 5/20-24: Exchanging cryo valves.

  • 5/27-6/2: Y arm mass lock.
  • 5/29: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (specially BS)

  • 6/3-6/14: Installation of TMS for ETMY
  • 6/8: Engineering run
  • ITMX
    • 5/22AM~: tuned off cryostat cooler, finesse measurement for Xarm

    • 5/22AM~: tuned off shield cooler, finesse measurement for Xarm

  • ETMX
    • 5/2: Cooling start

  • ITMY
    • 5/23AM~: tuned off cryostat cooler, finesse measurement for Yarm

  • ETMY
    • 5/17~: tuned off ETMY cryostat cooler

  • Long term:
    • 4/22-5/31: Yarm commissioning
    • 5/27-6/30: DRMI commissioning
    • 7/1-8/9: DRFPMI commissioning
    • 8/12-10/4: DRFPMI ASC
    • 10/7-11/15: Post Commissioning
    • 11/18-12/13: Noise hunting

Note

Night work

Weekend

Report of work

  • CRY, AOS: ETMs has no dew on 80K viewport but ITMs has still dew on their viewport.
  • VIS: tuning for suspensions. Still some suspensions has big motion.

Work plan

  • COM: Some of the suspension was shaking this morning.
    • X arm lock
    • Y arm lock
    • Finesse measurements for both X and Y arm. Specially Y arm is interesting with going back to cooling again.