Line 44: Line 44:
  * Needs finesse measurement.   * Needs finesse measurement for X arm.

2019/6/5(Wed.)

Schedule

  • 5/22-23: MZ release from PSL

  • 5/20-24: Exchanging cryo valves.

  • 5/27-6/2: Y arm mass lock. (not done yet)

  • 5/29: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (specially BS)

  • 6/3-6/14: Installation of TMS for ETMY
  • 6/8: Engineering run
  • ITMX
    • 5/22AM~: tuned off cryostat cooler, finesse measurement for Xarm

    • 5/22AM~: tuned off shield cooler, finesse measurement for Xarm

  • ETMX
    • 5/2: Cooling start

  • ITMY
    • 5/23AM~: tuned off cryostat cooler, finesse measurement for Yarm

  • ETMY
    • 5/17~: tuned off ETMY cryostat cooler

  • Long term:
    • 4/22-5/31: Yarm commissioning
    • 5/27-6/30: DRMI commissioning
    • 7/1-8/9: DRFPMI commissioning
    • 8/12-10/4: DRFPMI ASC
    • 10/7-11/15: Post Commissioning
    • 11/18-12/13: Noise hunting

Note

  • TMS installation this week.
  • Wednesday noon, we will have a Run meeting.

Night work

Weekend

Report of work

  • TMS installation started at ETMY.
  • Pressure of ITMX was recovered by changing cryo valve at duct cooler.
    • Needs finesse measurement for X arm.
  • PRX (PRM+ITMX) was Locked yesterday.
  • Michelson was Locked using AS port first time.
  • PRMI might be locked last night.
  • Sweeping modulation frequency to minimize RF-AM conversion.
  • Coil balance for 4 type A, and measuring TF.

Work plan

  • DGS: maintenance for installation whitening filter for iMC. iMC will be stopped.
    • Dolphin issue will be fixed today.