=== 2019/6/17(Mon.) ===

==== Schedule ====
 * --(5/22-23: MZ release from PSL)--
 * --(5/20-24: Exchanging cryo valves.)--
 * --(5/27-6/2: Y arm mass lock.)-- (not done yet) 
 * --(5/29: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (specially BS) )--
 * --(6/3-6/8: Installation of TMS for ETMY)--
 * --(6/8: Engineering run)--

 * ITMX

 * ETMX

 * ITMY

 * ETMY

 * Long term:
  * --(4/22-5/31: Yarm commissioning)--
  * 5/27-6/30: DRMI commissioning
  * 7/1-8/9: DRFPMI commissioning
  * 8/12-10/4: DRFPMI ASC
  * 10/7-11/15: Post Commissioning
  * 11/18-12/13: Noise hunting


==== Note ====
 * Please reduce the number or speed of 16kHz channels.

==== Night work ====

==== Weekend ====

==== Report of work ====
 * COM: PRM position should be moved ~5mm.
 * COM: SRM position should be moved ~10mm.

 * COM: Gouy phase of PRC has 30degree +/- few degree difference from the design.
  * We should move ~2mm to achieve design PRC Gouy phase.
  * PR3 will be moved ~2mm on Tuesday. We like to keep PR2 to avoid complexity.

 * COM: Gouy phase of SRC has 48degree +/- 2 degree difference from the design.
  * We should move ~10mm to achieve design SRC Gouy phase.
  * We have to open chamber if we correct 1cm order.




==== Work plan ====
 * IOO: FSS measurement in the daytime.
 * CRY: ETMY damping work in the daytime.