=== 2019/6/24(Fri.) === === 2019/6/24(Mon.) ===

2019/6/24(Mon.)

Schedule

  • 6/18 Move PR3

  • 6/19 DRMI locked.
  • ITMX
  • ETMX
    • 6/21: Stop cooler.
  • ITMY
  • ETMY
    • 6/20: Stop cooler
    • 7/1: Open chamber
  • Long term:
    • 4/22-5/31: Yarm commissioning

    • 5/27-6/30: DRMI commissioning
    • 7/1-8/9: DRFPMI commissioning
    • 8/12-10/4: DRFPMI ASC
    • 10/7-11/15: Post Commissioning
    • 11/18-12/13: Noise hunting

Note

  • Please reduce the number or speed of 16kHz channels.

Night work

Weekend

Report of work

  • Polarization shift was seen in PRC. Pure S pol. was confirmed at POP. Retuning beams from both ITMX and ITMY have 10% P component.
    • PR gain was only 3.

Work plan

  • Nitrogen will be added at ETMY to increase speed of temperature up.

KAGRA/Commissioning/DailyWork/2019-06-24 (last edited 2019-06-25 10:57:10 by OsamuMiyakawa)