=== 2019/6/24(Mon.) === ==== Schedule ==== * --(6/18 Move PR3)-- * 6/19 DRMI locked. * ITMX * ETMX * 6/21: Stop cooler. * ITMY * ETMY * 6/20: Stop cooler * 7/1: Open chamber * Long term: * --(4/22-5/31: Yarm commissioning)-- * 5/27-6/30: DRMI commissioning * 7/1-8/9: DRFPMI commissioning * 8/12-10/4: DRFPMI ASC * 10/7-11/15: Post Commissioning * 11/18-12/13: Noise hunting ==== Note ==== * Please reduce the number or speed of 16kHz channels. ==== Night work ==== ==== Weekend ==== ==== Report of work ==== * Polarization shift was seen in PRC. Pure S pol. was confirmed at POP. Retuning beams from both ITMX and ITMY have 10% P component. * PR gain was only 3. ==== Work plan ==== * Nitrogen will be added at ETMY to increase speed of temperature up.