=== 2019/6/26(Wed.) === ==== Schedule ==== * --(6/18 Move PR3)-- * 6/19: DRMI locked. * 6/21: polarization issue found. * ITMX * ETMX * 6/21: Stop cooler. * ITMY * ETMY * 6/20: Stop cooler * 6/28: Open chamber * Long term: * --(4/22-5/31: Yarm commissioning)-- * 5/27-6/30: DRMI commissioning * 7/1-8/9: DRFPMI commissioning * 8/12-10/4: DRFPMI ASC * 10/7-11/15: Post Commissioning * 11/18-12/13: Noise hunting ==== Note ==== * Please reduce the number or speed of 16kHz channels. ==== Night work ==== ==== Weekend ==== ==== Report of work ==== * COM: Loss by clipping was measured as less than 1%. * Type A, CRY: ETMY temperature is 177K. * VAC monitor was not correct but no it is working. * IOO: working on ISS second loop in the daytime. * DET: Glitch information is now available. ==== Work plan ==== * DGS: maintenance today for exchanging DC-DC power supply on IO chassis.