=== 2019/7/1(Tue.) === === 2019/7/2(Tue.) ===

2019/7/2(Tue.)

Schedule

  • 6/18 Move PR3

  • 6/19: DRMI locked.
  • 6/21: polarization issue found.
  • ITMX
  • ETMX
    • 6/21: Stop cooler.
  • ITMY
  • ETMY
    • 6/20: Stop cooler
    • 6/28: Open chamber
  • Long term:
    • 4/22-5/31: Yarm commissioning

    • 5/27-6/30: DRMI commissioning

    • 7/1-8/9: FPMI/DRFPMI commissioning
    • 8/12-10/4: ASC
    • 10/7-11/15: Post Commissioning
    • 11/18-12/13: Noise hunting

Note

  • Please reduce the number or speed of 16kHz channels.

Night work

Weekend

Report of work

  • Type A: ETMY was fixed by opening chamber. Clamp was added to be more tight.
    • Needs light to fix position.
    • Surface of ITMY was fogged on Sunday. We need to check and wait for a while.
    • CRT: closing ETMY after alignment done
  • COM: Try to lock PRX for checking beam shape.

Work plan

  • DMG: Try to connect to the additional space on second E18.
  • Type A: Oplev of ITMY seems to be something wrong and it will be fixed

KAGRA/Commissioning/DailyWork/2019-07-02 (last edited 2019-07-03 09:20:49 by OsamuMiyakawa)