=== 2019/7/2(Tue.) === ==== Schedule ==== * --(6/18 Move PR3)-- * 6/19: DRMI locked. * 6/21: polarization issue found. * ITMX * ETMX * 6/21: Stop cooler. * ITMY * ETMY * 6/20: Stop cooler * 6/28: Open chamber * Long term: * --(4/22-5/31: Yarm commissioning)-- * --(5/27-6/30: DRMI commissioning)-- * 7/1-8/9: FPMI/DRFPMI commissioning * 8/12-10/4: ASC * 10/7-11/15: Post Commissioning * 11/18-12/13: Noise hunting ==== Note ==== * Please reduce the number or speed of 16kHz channels. ==== Night work ==== ==== Weekend ==== ==== Report of work ==== * Type A: ETMY was fixed by opening chamber. Clamp was added to be more tight. * Needs light to fix position. * Surface of ITMY was fogged on Sunday. We need to check and wait for a while. * CRT: closing ETMY after alignment done * COM: Try to lock PRX for checking beam shape. ==== Work plan ==== * DMG: Try to connect to the additional space on second E18. * Type A: Oplev of ITMY seems to be something wrong and it will be fixed