=== 2019/7/5(Fri.) === ==== Schedule ==== * ~7/31: Trial for DRMI with polarization. * 7/6~: Trial for mass lock * ITMX * ETMX * ITMY * 7/4: Turbo pump on * ETMY * 7/4: Turbo pump on * Long term: * --(4/22-5/31: Yarm commissioning)-- * --(5/27-6/30: DRMI commissioning)-- * 7/1-8/9: FPMI/DRFPMI commissioning * 8/12-10/4: ASC * 10/7-11/15: Post Commissioning * 11/18-12/13: Noise hunting ==== Note ==== * Please reduce the number or speed of 16kHz channels. * GV of BS side can be opened on 7/5, but still please do not oped are side. ==== Night work ==== ==== Weekend ==== ==== Report of work ==== * VAC: Turbo pump are tuned on for ITMY and ETMY yesterday. * COM: During X arm lock, dropping transmitted light power was seen by factor of ~2. * Instability was seen on locking X-arm * Type B: Aluminum foil wind shield for OpLev is being put on SRM now. * CAL: MICH calibration is going on. * PEM: Whether information is now recorded into the frame file. * Noise budget for PEM by turning on/off pump switch will be done today. * Finding beam position program is being implemented. ==== Work plan ====