=== 2019/7/13(Sat.) === ==== Schedule ==== * ~7/31: Trial for DRMI with polarization. * 7/6~: Trial for mass lock * ITMX * ETMX * ITMY * 7/4: Turbo pump on * ETMY * 7/4: Turbo pump on * Long term: * --(4/22-5/31: Yarm commissioning)-- * --(5/27-6/30: DRMI commissioning)-- * 7/1-8/9: FPMI/DRFPMI commissioning * 8/12-10/4: ASC * 10/7-11/15: Post Commissioning * 11/18-12/13: Noise hunting ==== Note ==== * Please reduce the number or speed of 16kHz channels. * GV of BS side can be opened on 7/5, but still please do not oped are side. ==== Night work ==== ==== Weekend ==== ==== Report of work ==== * OLTF of MICH is being measured for ER2. * DGS: 16Hz comb was seen at BS OpLev at lease, so restated daqd, the fixed. * CAL: Low latency data transfer test will be done during ER2. * Infrastructure should be prepared well like data transfer, low latency... * DET: Omicron trigger is ready. Low latency signals should be almost real time, before joining O3. * DAT: Offline data analysis takes ~1day delay. ==== Work plan ==== * PEM: Environmental signal injection is planned after ER2 done. * CAL: Hardware injection is planned after ER2 done. * Needs ~30min for PEM, few min for CAL. Actuator efficiency of ITMs. * SEO: Needs check list before going observation mode. Entering mine. * Public data alert notification in the control system by speaking-> low latency group + DET