=== 2019/7/17(Wed.) === ==== Schedule ==== * ~7/31: Trial for DRMI with polarization. * 7/6~: Trial for mass lock * ITMX * ETMX * ITMY * ETMY * Long term: * --(5/27-6/30: DRMI commissioning)-- * 7/1-8/9: FPMI/DRFPMI commissioning * 8/12-10/4: ASC * 10/7-11/15: Post Commissioning * 11/18-12/13: Noise hunting ==== Note ==== * We have 1pm meeting more seriously. It will discuss next 24 house commissioning plan. * Please write down klog when your work is done and if you will have something to be announced. ==== Night work ==== ==== Weekend ==== ==== Report of work ==== * Y arm mass lock had some progress on suppressing error signal. Not ==== Work plan ==== * Coil driver for mass lock will be upgrade to have more current. * SR3 noise will be checked and probably power supply will be exchanged. * OMC will be extracted in the morning. * DGS: maintenance for exchanging DC power supply for IO chassis for SR3 and SR2. * Team PC exchange will be postponed. * Type A model will be restarted.