=== 2019/7/24(Wed.) === ==== Schedule ==== * ~7/31: Trial for DRMI with polarization. * 7/6~: Trial for mass lock * ITMX * ETMX * ITMY * ETMY * Long term: * 7/1-8/9: FPMI/DRFPMI commissioning * 8/12-10/4: ASC * 10/7-11/15: Post Commissioning * 11/18-12/13: Noise hunting ==== Note ==== ==== Night work ==== ==== Weekend ==== ==== Report of work ==== * Temperature drift affected IFO commissioning. So tried ALS signal handling off to TRX and TRY. * SR3 H2 noise investigation is still going on. * Suppressing 80mHz of yaw by feeding back the MN oplev signal was done. * OMC work for alignment. Control system was implemented. * temperature fluctuation at all the central area specially around BS for 0.6C with 20hours period. ==== Work plan ==== * DGS maintenance * BIO cards installation. * Replacing RT-PCs of SR or PR * Modification of Type A model. * Temperature maintenance in the afternoon. * MZ work (Guiguo). * OMC work in the morning.