=== 2019/7/30(Mon.) ===

==== Schedule ====
 * ~7/31: Trial for DRMI with polarization.
 * 7/6~: Trial for mass lock

 * ITMX

 * ETMX

 * ITMY

 * ETMY


 * Long term:
  * 7/1-8/9: FPMI/DRFPMI commissioning
  * 8/12-10/4: ASC
  * 10/7-11/15: Post Commissioning
  * 11/18-12/13: Noise hunting


==== Note ====

==== Night work ====

==== Weekend ====

==== Report of work ====
 * ALS: Installed Optics for fiber noise cancel. It looked too fast fringe.
 * Type A: Updated Type A suspension models.
 * Type B: SR3 and SR2 RMS motion were measured. It was less than 0.5urad. 

 
 
==== Work plan ====
 * ITMY: Opening ITMY chamber and woking inside by CRY (Tomaru, Ushiba, Yamada) and VIS to fix motor and to check BF... (Okutomi, Sato, Fujii)
 * ALS: Needs more work, in the PSL in the morning, and all area in the afternoon. (Enomoto, Sugimoto)
 * Connecting tube on the AS table. (Michimura)
 * BS and SRM will be measured in the morning. (Fabian)