=== 2019/7/30(Mon.) === === 2019/7/30(Tue.) ===

2019/7/30(Tue.)

Schedule

  • ~7/31: Trial for DRMI with polarization.
  • 7/6~: Trial for mass lock
  • ITMX
  • ETMX
  • ITMY
  • ETMY
  • Long term:
    • 7/1-8/9: FPMI/DRFPMI commissioning
    • 8/12-10/4: ASC
    • 10/7-11/15: Post Commissioning
    • 11/18-12/13: Noise hunting

Report of work

  • ALS: Installed Optics for fiber noise cancel. It looked too fast fringe.
  • Type A: Updated Type A suspension models.
  • Type B: SR3 and SR2 RMS motion were measured. It was less than 0.5urad.

Work plan

  • ITMY: Opening ITMY chamber and woking inside by CRY (Tomaru, Ushiba, Yamada) and VIS to fix motor and to check BF... (Okutomi, Sato, Fujii)
  • ALS: Needs more work, in the PSL in the morning, and all area in the afternoon. (Enomoto, Sugimoto)
  • Connecting tube on the AS table. (Michimura)
  • BS and SRM will be measured in the morning. (Fabian)

KAGRA/Commissioning/DailyWork/2019-07-30 (last edited 2019-07-31 08:59:30 by OsamuMiyakawa)