=== 2019/7/30(Tue.) === ==== Schedule ==== * ~7/31: Trial for DRMI with polarization. * 7/6~: Trial for mass lock * ITMX * ETMX * ITMY * ETMY * Long term: * 7/1-8/9: FPMI/DRFPMI commissioning * 8/12-10/4: ASC * 10/7-11/15: Post Commissioning * 11/18-12/13: Noise hunting ==== Report of work ==== * ALS: Installed Optics for fiber noise cancel. It looked too fast fringe. * Type A: Updated Type A suspension models. * Type B: SR3 and SR2 RMS motion were measured. It was less than 0.5urad. ==== Work plan ==== * ITMY: Opening ITMY chamber and woking inside by CRY (Tomaru, Ushiba, Yamada) and VIS to fix motor and to check BF... (Okutomi, Sato, Fujii) * ALS: Needs more work, in the PSL in the morning, and all area in the afternoon. (Enomoto, Sugimoto) * Connecting tube on the AS table. (Michimura) * BS and SRM will be measured in the morning. (Fabian)