=== 2019/7/31(Wed.) === ==== Schedule ==== * ~7/31: Trial for DRMI with polarization. * 7/6~: Trial for mass lock * ITMX * ETMX * ITMY * ETMY * Long term: * 7/1-8/9: FPMI/DRFPMI commissioning * 8/12-10/4: ASC * 10/7-11/15: Post Commissioning * 11/18-12/13: Noise hunting ==== Report of work ==== * Finesse of X arm became low to ~1000. * Transmitted light was low. * ETMX has frost again. * We decided to turn off the cooler. * ITMY motor was stuck actually. It reached to one direction of the limit of range. It was fixed. * More continuous works are planed. * Magnet was not off. Needs more investigation. ==== Work plan ==== * DGS maintenance for exchanging k1dc0, adding BIO cards to k1ioo1 for ALS control (Yamamoto, Oshino) * VIS should go safe mode. (Fabian) * DC power source will be exchanged at ALS0 and ALS1 rack. (Kamiizumi) * AOS: Checking and exchanging laser for oplev, ETMY or PRM. * Type B: Releasing FR for all suspensions after finishing maintenance or afternoon.