Line 10: Line 10:
|| ||DGS, CAL (30min)||Yamamoto||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=xxxx|x]] ||
|| ||PEM: (30min)||Nagano||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=xxxx|x]] ||
|| ||DGS, CAL (30min)||Yamamoto||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=xxxx|x]]|| ||
|| ||PEM: (30min)||Nagano||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=xxxx|x]]|| ||

Meeting for looking back to phase1 for future of KAGRA

  • Date and time: 2018/5/28 10AM~17PM
  • Location: Toyama University multi purpose hall

Time

Topic/susbsystem

Speaker

File

Memo

10:00~

Commissioning overview (15min)

Miyakawa

x

Commissioning work (30min)

Enomoto

x

DGS, CAL (30min)

Yamamoto

x

PEM: (30min)

Nagano

x

Expert call: (15min)

Izumi/Miyoki

x

12:00-13:00

Lunch

13:00~

GW office: (30min)

Takayama

x

VIS installation: (30min)

Aso

x

VIS tuning: (20min)

Shoda

x

CRY installation: (30min)

Tomaru

x

CRY tuning: (20min)

Miyamoto

x

Heat ling: (20min)

Yamada

x

AOS: (30min)

Akutsu

x

VAC: (30min)

Kimura

x

Others: (30min)

x