Differences between revisions 5 and 6
Revision 5 as of 2018-05-24 12:36:08
Size: 2023
Comment:
Revision 6 as of 2018-05-24 12:38:44
Size: 2056
Comment:
Deletions are marked like this. Additions are marked like this.
Line 14: Line 14:
||13:00~||GW office: (30min)||Takayama||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=xxxx|x]]|| || ||13:00~||GW office: (15min)||Takayama||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=xxxx|x]]|| ||
Line 19: Line 19:
|| ||||Break time (10min)||||||

Meeting for looking back to phase1 for future of KAGRA

  • Date and time: 2018/5/28 10AM~17PM
  • Location: Toyama University multi purpose hall

Time

Topic/susbsystem

Speaker

File

Memo

10:00~

Commissioning overview (15min)

Miyakawa

x

Commissioning work (30min)

Enomoto

x

DGS, CAL (30min)

Yamamoto

x

PEM: (30min)

Nagano

x

Expert call: (15min)

Izumi/Miyoki

x

12:00-13:00

Lunch

13:00~

GW office: (15min)

Takayama

x

VIS installation: (30min)

Aso

x

VIS tuning: (20min)

Shoda

x

CRY installation: (30min)

Tomaru

x

CRY tuning: (20min)

Miyamoto

x

Break time (10min)

Heat link: (20min)

Yamada

x

AOS: (30min)

Akutsu

x

VAC: (30min)

Kimura

x

Others: (30min)

x

KAGRA/Commissioning/Meetings/Others/20180528/Phase1 (last edited 2018-05-28 15:21:47 by OsamuMiyakawa)