Line 53: Line 53:
  * duty factor
   * Total: 68.65%
   * 4/28: 81.66%
   * 4/29: 97.00%
   * 4/30: 90.36%
   * 5/01: 87.09%
   * 5/02: 86.88%
   * 5/03: 19.97%
   * 5/04: 33.58%
   * 5/05: 64.18%
   * 5/06: 55.36%

Summary of Phase 1 Measurements

  • Summary of Phase 1 measurements for bKAGRA Phase 1 paper.

Basic configurations

Michelson initial alignment

  • details of slit method
  • Tcam and baffle PD performance (details-> Tcam paper)

    • time delay, resolution ...
    • succeefully monitored the beam under cryo baffles/shields

Installation accuracy

Cryogenics

  • cooling curve (details -> CRY paper)

  • alignment drift during the cool down

Suspension characterization

Sensitivity and stability

Seismic noise, arm length drift

Hardware injection test

  • CBC injection(2018/4/30 Night shift)
  • CW injection(2018/5/2 Night shift)