Summary of Phase 1 Measurements

  • Summary of Phase 1 measurements for bKAGRA Phase 1 paper.

Basic configurations

Michelson initial alignment

  • details of slit method
  • Tcam and baffle PD performance (details-> Tcam paper)

    • Tcam update frequency ~1sec, resolution [Inoue]
    • Tcam resolution?
    • successfully monitored the beam under cryo baffles/shields

Installation accuracy

Cryogenics

  • cooling curve (details -> CRY paper) [Hasegawa?]

    • Platform, MN, IM, TM, shields
  • alignment drift, height change during the cool down

Suspension characterization

Sensitivity and stability

Seismic noise, arm length drift

Data acquisition, data transfer

  • latency, speed, total amount

Hardware injection test

  • CBC injection(2018/4/30 Night shift)
  • CW injection(2018/5/2 Night shift)