Differences between revisions 29 and 32 (spanning 3 versions)
Revision 29 as of 2018-05-08 15:39:42
Size: 5264
Comment:
Revision 32 as of 2018-05-09 23:25:18
Size: 5514
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Duration
  * officially (as Saito-san mentioned): Apr 28 9:00am to May 7 6:00am (GPS time: 1208908818-1209675618)
Line 7: Line 9:
  * 0.93W at PSL output
Line 35: Line 38:
 * initial alignment
  * https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7659

Summary of Phase 1 Measurements

  • Summary of Phase 1 measurements for bKAGRA Phase 1 paper.

Basic configurations

Michelson initial alignment

  • details of slit method
  • Tcam and baffle PD performance (details-> Tcam paper)

    • Tcam update frequency ~1sec, resolution [Inoue]
    • Tcam resolution?
    • successfully monitored the beam under cryo baffles/shields

Installation accuracy

Cryogenics

  • cooling curve (details -> CRY paper) [Hasegawa?]

    • Platform, MN, IM, TM, shields
  • alignment drift, height change during the cool down

Suspension characterization

Sensitivity and stability

Seismic noise, arm length drift

Data acquisition, data transfer

  • latency, speed, total amount

Hardware injection test

  • CBC injection(2018/4/30 Night shift)
  • CW injection(2018/5/2 Night shift)

KAGRA/Commissioning/Phase1/Operation/MeasurementsSummary (last edited 2018-10-01 20:39:54 by YutaMichimura)