= Check list for vacuum test in the Center area = * Term: 2018/3/7~2018/3/23 === Schedule === * 2018/3/12-14: ducts connection * 2018/3/15-16: pump down * 2018/3/19-23: leak check ------ == Check items == Each item should have following format; * item (checking date, checking person) -> Planned at 2018/3/XX Once the item has been checked, it will be like: * --(item)-- (2018/3/10, Somebody) ---- === Alignment === * --(Beam check at ETMX)-- (2018/3/5, Enomoto) * --(Beam check at ETMY)-- (2018/3/6, Enomoto) * --(Beam check at REFL)-- (2018/3/6, Enomoto) * --(PD movement from BS are to REFL area)-- (2018/3/7, Enomoto) === Preparation of monitors during pump down === * Oplev monitor check for PRM (2018/3/XX Kokeyama) -> 2018/3/14 planed by Kokeyama * --(Oplev monitor check for PR2)-- (2018/3/14 Enomoto) * --(Oplev monitor check for PR3)-- (2018/3/14 Enomoto) * Oplev monitor check for BS (2018/3/14 Enomoto) -> 2018/3/14 planed * --(PD for REFL)-- (2018/3/14 Enomoto) * --(GigE camera for IMMT1)-- (2018/3/7 Kokeyama) * --(GigE camera for IMMT2)-- (2018/3/7 Kokeyama) * --(GigE camera for PR2)-- (2018/3/7 Kokeyama) * --(GigE camera for PR3)-- (2018/3/7 Kokeyama) * --(GigE camera for BS)-- (2018/3/7 Kokeyama) * --(GigE camera for REFL)-- (2018/3/ Kokeyama) * --(Tcam for IXC)-- (2018/3/14 Yokozawa) * --(Tcam for IYC)-- (2018/3/14 Yokozawa) * --(Vacuum gage)-- (2018/3/18 Uchiyama) * --(真空槽の傾きをdial gaugeで測る準備)-- (2018/3/14 Kimura) ---- === Other checks before pump down === * Re-checkin beam before pump down (2018/3/XX Enomoto) -> Planned at 2018/3/14 night * --(Control for gate valve open/close at Y-end)-- (2018/3/14 Uchiyama) * Monitor for gate valve open/close (2018/3/XX Uchiyama) -> Planned at 2018/3/XX * Star pump down(2018/3/XX Uchiyama) -> Planned at 2018/3/15 === Pump down (Kimura) === i. 真空計 ON (2018/3/XX, Kimura) -> Planned at 2018/3/15 * 粗挽きポンプスタート (2018/3/XX, Kimura) -> Planned at 2018/3/15 * ターボポンプ冷却水循環装置スタート (2018/3/XX, Kimura) -> Planned at 2018/3/16 * ターボポンプスタート (2018/3/XX, Kimura) -> Planned at 2018/3/16 * リーク試験 (2018/3/XX, Kimura) -> Planned at 2018/3/19-21 * (リーク判定 < 1x10^-10 Pa・m^3/s) === Checks during pump down === * Vacuum monitor (2018/XX/XX Uchiyama) -> Planned at 2018/3/XX * Oplevで随時アラインメントのチェック (2018/XX/XX Enomono) -> Planned at 2018/3/XX * 真空槽の傾きをdial gaugeを見続ける (2018/3/XX, Kimura) -> Planned at 2018/3/XX ---- === Connection status (Uchiyama) === {{attachment:KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter/図2_180208_中央真空系.png||width=800}} ==== GVmc ==== * --(hemisphere(VM7950)φ 1000/400 L 570)-- (2018/3/14 Kimura) ==== IFI ==== * --(pump port (VL7862C) φ 800 L 1285)-- (2018/3/14 Kimura) ==== IMM ==== * --(bellows (VL7952A) φ 400 L 555)-- (2018/3/14 Kimura) ==== PRM ==== * --(bellows (VL7856) φ 800 L 620)-- (2018/3/14 Kimura) * --(pump port (VL8423) φ 800 L 760)-- (2018/3/14 Kimura) * --(bellows (VL7856) φ 800 L 620)-- (2018/3/14 Kimura) ==== PR3 ==== * --(bellows (VL7856) φ 800 L 620)-- (2018/3/14 Kimura) * --(pump port (VL8428) φ 800 L 8225)-- (2018/3/14 Kimura) * --(bellows (VL7856) φ 800 L 620)-- (2018/3/14 Kimura) ==== PR2 ==== * --(bellows (VL7856) φ 800 L 620)-- (2018/3/14 Kimura) * --(pump port (VL8425) φ 800 L 1740)-- (2018/3/14 Kimura) * --(bellows (VL7856) φ 800 L 620)-- (2018/3/14 Kimura) ==== BS ==== * --(bellows (VL7855) φ 1000 L 620)-- (2018/3/14 Kimura) * --(pump port (VL8419) φ 1000 L 4376)-- (2018/3/14 Kimura) * --(bellows (VL7857D) φ 1000 L 620)-- (2018/3/14 Kimura) ==== GVbsx ==== ==== BS ==== * --(bellows/tube (VL7860) φ 1000 L 1765)-- (2018/3/14 Kimura) * --(pump port (VL7861) φ 1000 L 1400)-- (2018/3/14 Kimura) ==== GVbsy ==== ==== BS ==== * --(blank φ 800)-- (2018/3/14 Kimura) ---- === 以下、VIS,IOOに他に閉めるべきフランジがないかどうか確認してもらって作ったリスト === * IFI, IMMの真空容器の状況 * --(IFF の、プラスY側のφ400のフランジ。Oringはついてないのでつける必要がある。)-- (2018/3/14 Kimura) * --(IMMの、マイナスY側のφ400のフランジ。Oringはついてないのでつける必要がある。)-- (2018/3/14 Kimura) * VIS関連チャンバーの状況 * BS: * --(トップフランジ: O-ringを入れてあるが,養生テープが貼ったまま。締められていない。)-- (2018/3/14 Kimura) * --(上部サービスフランジ2枚(添付写真): 蓋は付いているが,締めていない。)-- (2018/3/14 Kimura) * --(下部サービスフランジ2枚(添付写真): 蓋は付いているが,締めていない。)-- (2018/3/14 Kimura) * --(フィードスルーフランジ: ガスケットは入れてあるが,ちゃんと締めていない。)-- (2018/3/14 Kimura) * --(フィードスルーフランジを取り付けるポートに付いているメクラフランジ: ちゃんと締めていない。ガスケットも入っていないかもしれない。)-- (2018/3/14 Kimura) * PRM: * --(トップフランジ: O-ringが入っていない。)-- (2018/3/7 Kimura) * --(フィードスルーフランジ: ガスケットは入れてあるが,ちゃんと締めていない。)-- (2018/3/7 Kimura) * --(各側面フランジをクロークランプにより締め付ける。)-- (2018/3/14 Kimura) * PR2: * --(トップフランジ: O-ringは入っているが締めていない。)-- (2018/3/5締めた Uchiyama) -> Planned at 2018/3/XX * --(フィードスルーフランジ: ガスケットは入れてあるが,ちゃんと締めていない。)-- (2018/3/14 Kimura) * --(グリーン入射用ビューポートのフランジ: ガスケットは入れてあるが,ちゃんと締めていない。)-- (2018/3/14 Kimura) * --(PR2側面フランジのユーティリティ用フランジ(ICF203、空気導入口として使用)の交換 1箇所の締め付け)-- (2018/3/7 Kimura) * --(各側面フランジをクロークランプにより締め付ける。)-- (2018/3/14 Kimura) * PR3: * --(トップフランジ: O-ringは入っているが締めていない。)--(2018/3/5締めた Uchiyama) -> Planned at 2018/3/XX * --(フィードスルーフランジ: ガスケットは入れてあるが,ちゃんと締めていない。)-- (2018/3/14 Kimura) * --(各側面フランジをクロークランプにより締め付ける。)-- (2018/3/14 Kimura)