Line 1: | Line 1: |
== Check list for ETMX vacuum 20180314 == | == Check list for ETMX vacuum in spring, 2018 == * Term: ~2018/4/20 === Schedule === * 2018/3/26-4/6 : ETMX control test * 2018/4/9-12 : Closing EXC * 2018/4/5(Thur) 12:30 at fan hut. * 2018/4/11(Wed) 12:30 at fan hut. * 2018/4/12- : pump down * 2018/4/18-20: leak check ------ |
Line 12: | Line 25: |
* Beam check at ETMX (2018/X/XX, Enomoto) * Beam check at ETMY (2018/X/XX, Enomoto) * Beam check at REFL (2018/X/XX, Enomoto) |
* Beam check at ETMX just before pump down(not possible with baffle PD through gate valve?) (2018/X/XX, Enomoto) -> Planned at 2018/4/11 * Beam check at ETMY just before pump down (2018/X/XX, Enomoto) -> Planned at 2018/4/11 * Beam check at REFL just before pump down (2018/X/XX, Enomoto) -> Planned at 2018/4/11 |
Line 19: | Line 32: |
* Oplev monitor check for PRM (2018/X/XX Enomoto) -> Planned at 2018/X/XX * Oplev monitor check for PR2 (2018/X/XX Enomoto) -> Planned at 2018/X/XX * Oplev monitor check for PR3 (2018/X/XX Enomoto) -> Planned at 2018/X/XX * Oplev monitor check for BS (2018/X/XX Enomoto) -> Planned at 2018/X/XX * PD fot REFL (2018/3/XX Kokeyama) -> Planned at 2018/X/XX * GigE camera for IMMT1 (2018/X/XX Kokeyama) -> Planned at 2018/X/XX * GigE camera for IMMT2 (2018/X/XX Kokeyama) -> Planned at 2018/X/XX * GigE camera for PR2 (2018/X/XX Kokeyama) -> Planned at 2018/X/XX * GigE camera for PR3 (2018/X/XX Kokeyama) -> Planned at 2018/X/XX * Tcam for ETMX (2018/X/XX Inoue) -> Planned at 2018/3/XX * Vacuum gage (2018/XX/XX Uchiyama) -> Planned at 2018/X/XX * 真空槽の傾きをdial gaugeで測る。 (2018/3/XX Tomaru, Suzuki, Kimura) -> Planned at 2018/3/XX |
* Oplev monitor check for PRM (2018/X/XX Enomoto) -> Planned at 2018/4/11 * Oplev monitor check for PR2 (2018/X/XX Enomoto) -> Planned at 2018/4/11 * Oplev monitor check for PR3 (2018/X/XX Enomoto) -> Planned at 2018/4/11 * Oplev monitor check for BS (2018/X/XX Enomoto) -> Planned at 2018/4/11 * PD fot REFL (2018/4/XX Enomoto) -> Planned at 2018/4/11 * GigE camera for IMMT1 (2018/X/XX Kokeyama) -> Planned at 2018/4/11 * GigE camera for IMMT2 (2018/X/XX Kokeyama) -> Planned at 2018/4/11 * GigE camera for PR2 (2018/X/XX Kokeyama) -> Planned at 2018/4/11 * GigE camera for PR3 (2018/X/XX Kokeyama) -> Planned at 2018/4/11 * GigE camera for BS (2018/X/XX Kokeyama) -> Planned at 2018/4/11 * GigE camera for REFL (2018/X/XX Kokeyama) -> Planned at 2018/4/11 * Tcam for ETMX (2018/X/XX Inoue) -> Planned at 2018/4/11 * Tcam for ETMY (2018/X/XX Inoue) -> Planned at 2018/4/11 * --(Tcam for ITMX)-- (2018/4/5 Inoue) * --(Tcam for ITMY)-- (2018/4/5 Inoue) * Illuminator for ETMX (2018/X/XX Inoue) -> Planned at 2018/4/11 * --(Illuminator for ETMY) (2018/4/5 Inoue) * Vacuum gage for E end (2018/4/XX Inoue) -> Planned at 2018/4/16 * Vacuum gage for X arm (2018/4/XX Inoue) -> Planned at 2018/4/16 * Vacuum gage for Center area (2018/4/XX Uchiyama) -> Planned at 2018/4/16 * 真空槽の傾きをdial gaugeで測る。 (2018/4/XX Tomaru, Suzuki, Kimura) -> Planned at 2018/4/13 * Xend 機器制御 for status monitors (2018/4/XX Tomaru, Suzuki, Kimura) -> Planned at 2018/4/5, 6 * Vacuum gauge monitor at the control room at least one location (2018/X/XX Uchiyama, Kimura, Inoue, Miyoki) -> Planned at 2018/4/XX |
Line 37: | Line 65: |
* --(EQ stopの隙間のチェック5mm程度)--(2018/1/17 都丸、牛場) * 1/26に真空引き後、防振系の動作チェック(2018/XX/XX 高橋、牛場) -> 2018/1/23予定 * 冷却開始前にビーム再チェック(2018/XX/XX 和泉) -> 2018/1/26予定 * アームのポンプスタート(2018/XX/XX 内山) -> 2018/??/??予定 * アームの真空度のチェック(2018/XX/XX 内山) -> 2018/??/??予定 * ゲードバルブの動作チェック(2018/XX/XX 内山) -> 2018/??/??予定 * ゲードバルブの開閉モニター (2018/XX/XX 内山) -> 2018/??/??予定 |
* EQ stopの隙間のチェック5mm程度 (2018/X/XX, Ushiba, Tomaru) -> (2018/4/11 planed) * 真空引き後、防振系の動作チェック (2018/X/XX, Enomoto) -> (2018/4/13 planed) * EXA ゲードバルブの動作チェック (2018/X/XX, Uchiyama) -> (2018/4/20 planed) * EXA ゲードバルブの開閉モニター to 機器制御 (今回は必須でないかもしれない) (2018/X/XX, Uchiyama) -> (2018/4/20 planed) |
Line 47: | Line 71: |
* Tuning of BF (2018/X/XX, Takahashi) -> (2018/X/XX planed) * Tuning of F3 (2018/X/XX, Takahashi) -> (2018/X/XX planed) * Tuning of TF (2018/X/XX, Takahashi) -> (2018/X/XX planed) * Tuning of position of BF damper (2018/X/XX, Takahashi) -> (2018/X/XX planed) * Centering IP (2018/X/XX, Takahashi) -> (2018/X/XX planed) |
* Fishing rodの動作チェック (2018/X/XX, Takahashi) -> (2018/4/6 planed, without camera) * --(Tuning of BF)-- (2018/3/26, Takahashi) * --(Tuning of F3)-- (2018/3/27, Takahashi) * --(Tuning of TF)-- (2018/3/27, Takahashi) * --(Tuning of position of BF damper)-- (2018/3/28, Takahashi) * --(Centering IP)-- (2018/3/27, Takahashi) |
Line 54: | Line 79: |
* トップ真空槽蓋閉め (2018/X/XX, Takahashi) -> (2018/X/XX planed) * トップ真空槽ボルト閉め (2018/X/XX, Kimura) -> (2018/X/XX planed) * クロス菅ボルト閉め (2018/X/XX, Kimura) -> (2018/X/XX planed) * IPのDC調整 (2018/X/XX, Takahashi) -> (2018/X/XX planed) * BFのdamping制御 (2018/X/XX, Ushiba) -> (2018/X/XX planed) * BF FRによるmirrorの高さ調整 (2018/X/XX, Takahashi) -> (2018/X/XX planed) * BF yaw picomotorによるmirrorのyaw調整 (2018/X/XX, Takahashi) -> (2018/X/XX planed) * 事前にTypeA、Cryopayloadのアラインメント機構が動くかどうか確認する。 (2018/X/XX, ??) -> (2018/X/XX planed) * BF温度計つなぎこみ (2018/X/XX, Takahashi, Ushiba) -> (2018/X/XX planed) |
* --(トップ真空槽蓋閉め)-- (2018/3/28, Takahashi) * トップ真空槽ボルト閉め (2018/X/XX, Kimura) -> (2018/4/10 planed) * クロス菅ボルト閉め (2018/X/XX, Kimura) -> (2018/4/10 planed) * IPの制御 (2018/4/XX, Okutomi) -> (2018/X/XX re-check) * --(BFのdamping制御)-- (2018/4/2, Okutomi) -> (2018/X/XX planed) * --(BF FRによるmirrorの高さ調整)-- (2018/4/5, Takahashi) * --(BF yaw picomotorによるmirrorのyaw調整)-- (2018/4/5, Ushiba) * --(事前にTypeA、Cryopayloadのアラインメント機構が動くかどうか確認する。)-- (2018/4/5, Ushiba) * BF温度計つなぎこみ (2018/X/XX, Takahashi, Ushiba) -> (2018/4/6 planed) |
Line 65: | Line 91: |
* --(鏡板取付前の変換フランジ取付)-- (2017/12/18, 木村) * --(輻射シールドのシャッター開確認)-- (2017/12/19, 木村) * --(当該部のSuper Insulation(SI)取り外し確認)-- (2018/1/23, 木村) * --(鏡板取付後のビューポート取付)-- ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=3909|2017/12/27]], 阿久津) * --(Oplev用の島?取付)-- ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=3910|2017/12/27]], 阿久津) === EYAチェンバー周り (井上) === * --(フォトディテクターの取り外し)-- (2017/12/15, 横澤) * --(冷却と主ビーム観測に向けたTcamのセッティング)-- (2017/12/27, 井上, 横澤) * --(Gigeカメラの前の真空窓取り外しと取り付け)-- (2017/12/18, 井上) * (Gigeカメラのポートにはメタルガスケットが入っていないため、そのまま冷却をスタートしてしまうと真空漏れを起こしミラー表面を汚してしまう。) === EYV支持構造体のセット確認 === |
* 8K および 80Kシールドにつける窓類の取り付け (2018/4/xx, Ushiba) -> (2018/4/11 just before closing EXC door) * 輻射シールドのシャッター開確認 (2018/X/XX, Kimura) -> (2018/X/XX planed) * 当該部のSuper Insulation(SI)取り外し確認 (2018/X/XX, Kimura) -> (2018/X/XX planed) * 鏡板取付前の変換フランジ取付 (2018/X/XX, Kimura) -> (2018/4/9 planed) * 鏡板取付後のビューポート取付 (2018/X/XX, Akutsu) -> (2018/4/12 planed) * Oplev用の島取付 (2018/X/XX, Akutsu) -> (2018/4/12 planed) === EXAチェンバー周り (Inoue) === * フォトディテクターの取り外し (2018/X/XX, Yokozawa) -> (2018/3/27 planed) * GigEカメラの前の真空窓取り外しと取り付け (2018/X/XX, Inoue) -> (2018/4/5,6 planed) === EXV支持構造体のセット確認 === |
Line 80: | Line 104: |
* チェンバー本体用 3箇所 <- 真空引き前にフリーにする (2018/X/XX, 木村) | * --(チェンバー本体用 3箇所 <- 真空引き前にフリーにする)-- 今回はやらない |
Line 86: | Line 110: |
* --(EYV top flange)-- : VIS group (2018/1/24, 高橋) * --(EYAカメラ側鏡板閉止)-- (2018/1/22, 木村) * --(EYV chamber)-- : CRY group (2017/12/22, 木村+双葉工業) * --(クロス菅鏡板2箇所)-- : CRY group (2018/1/22, 高橋(ICRR)+双葉工業) * --(ICF253送風機接続ポート)--: CRY group (2018/1/22, 高橋(ICRR)+双葉工業) * --(φ800サイドフランジ)--: CRY group (2018/1/23, 都丸+双葉工業) * --(冷凍機NW-50フランジ交換)-- 4箇所: CRY group (2018/1/23, 木村) |
* EXA 鏡板閉止 (2018/4/XX, Kimura) -> (2018/4/XX planed) * EXV top flange: VIS group (2018/X/XX, Takahashi) -> (2018/X/XX planed) * --(EXV ICF flange交換 ICF203/NW50 変換フランジ -> ICF203ブランクフランジ)-- : VIS group (2018/3/28, Takahashi) * クロス菅鏡板2箇所: CRY group VIS group (2018/X/XX, Kimura) -> (2018/X/XX planed) * ICF253送風機接続ポート: CRY group (2018/X/XX, , Kimura) -> (2018/X/XX planed) * EXC鏡板2箇所: CRY group (2018/X/XX, Kimura) -> (2018/X/XX planed) * EXC ViewPort 4箇所?(鏡板2箇所、容器2箇所?):AOS (2018/X/XX, Akutsu, Ushiba) -> (2018/X/XX planed) * 冷凍機NW-50フランジ交換 4箇所: CRY group (2018/X/XX, Kimura) -> (2018/X/XX planed) * EXA ICF152 2箇所: cal group (2018/4/5-6, Inoue) -> (2018/X/XX planed) |
Line 95: | Line 122: |
* スタートさせる (2018/XX/XX, 都丸、麻生) -> 2018/1/23予定 | * スタートさせる (2018/XX/XX, 都丸、麻生) -> (2018/X/XX planed) |
Line 100: | Line 127: |
i. --(真空計2台 ON)-- (2018/1/23, 木村) * --(粗挽きポンプスタート)-- (2018/1/24, 木村) -> 2018/1/23朝予定 * --(大まかなリークチェック)-- (2018/1/24, 木村) 1/23に0.1気圧引いてそれが1/24朝まで保たれていたのでOK * --(ターボポンプ冷却水循環装置スタート)-- (2018/1/23, 木村) * --(ターボポンプスタート)-- (2018/1/24, 木村) 朝9時30分起動 * リーク試験 (2017/XX/XX, 木村、上田、高橋(icrr)) -> 2018/1/29,30予定 |
i. 真空計2台 ON (2018/X/XX, Kimura) -> (2018/X/XX planed) * 粗挽きポンプスタート (2018/X/XX, Kimura) -> (2018/X/XX planed) * 大まかなリークチェック (2018/X/XX, Kimura) -> (2018/X/XX planed) * ターボポンプ冷却水循環装置スタート (2018/X/XX, Kimura) -> (2018/X/XX planed) * ターボポンプスタート (2018/X/XX, Kimura) -> (2018/X/XX planed) * リーク試験 (2018/4/XX, Kimura) -> (2018/4/18 planed) |
Line 108: | Line 135: |
* EYA arm側ゲートバルブ動作チェック (2018/XX/XX, 木村) -> 2018/1/30夕予定? * EYA arm側ゲートバルブOPEN (2018/XX/XX, 木村) -> 2018/1/30夕予定? * メインレーザーを使ったバッフルPDの動作確認 (2018/XX/XX, 和泉?) -> 2018/1/30夕予定? * 冷却開始 i. ヘリウム圧縮機用冷却水循環装置 1次冷却水バルブ 開 (2017/XX/XX, 木村) -> 2018/1/25夕方予定 * ヘリウム圧縮機用冷却水循環装置 ON (2017/XX/XX, 木村) -> 2018/1/25夕方予定 * ヘリウム圧縮機 6台 ON (2017/XX/XX, 木村) -> 2018/1/25夕方予定 |
* EXA arm側ゲートバルブ動作チェック (2018/X/XX, Kimura) -> (2018/X/XX planed) * EXA arm側ゲートバルブOPEN (2018/X/XX, Kimura) -> (2018/X/XX planed) * メインレーザーを使ったバッフルPDの動作確認 (2018/X/XX, Enomoto) -> (2018/X/XX planed) |
Line 122: | Line 143: |
* --(PFのリリース(16箇所))--(2017/12/20, 牛場、都丸) * --(MNのリリース(16箇所))--(2017/12/20, 牛場、都丸) * --(MNRのリリース(16箇所))--(2017/12/20, 牛場、都丸) * --(IMのリリース(6箇所))--(2017/12/20, 牛場、都丸) * --(IMRのリリース(16箇所))--(2017/12/20, 牛場、都丸) * --(TMのリリース(16箇所))--(2017/12/20, 牛場、都丸) * --(TMRのリリース(15箇所))--(2017/12/20, 牛場、都丸) |
* PFのリリース(16箇所) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MNのリリース(16箇所) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MNRのリリース(16箇所) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IMのリリース(6箇所) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IMRのリリース(16箇所) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * TMのリリース(16箇所) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * TMRのリリース(15箇所) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) |
Line 131: | Line 152: |
* --(TM Op''''''Lev Pitch:キャリブレーション済み)--(2017/12/08,牛場、宮本) * --(TM Op''''''Lev Yaw:キャリブレーション済み)--(2017/12/08,牛場、宮本) * TM Op''''''Lev Length:未確認 -> 真空引き以降に予定 * --(IM PS H1:動作確認済み)--(2017/12/21,牛場、宮本) * --(IM PS H2:動作確認済み)--(2017/12/21,牛場、宮本) * --(IM PS H3:動作確認済み)--(2017/12/21,牛場、宮本) * --(IM PS V1:動作確認済み)--(2017/12/21,牛場、宮本) * --(IM PS V2:動作確認済み)--(2017/12/21,牛場、宮本) * --(IM PS V3:動作確認済み)--(2017/12/21,牛場、宮本) * --(MN PS H1:動作確認済み)--(2017/12/21,牛場、宮本) * --(MN PS H2:動作確認済み)--(2017/12/21,牛場、宮本) * --(MN PS H3:動作確認済み)--(2017/12/21,牛場、宮本) * --(MN PS V1:動作確認済み)--(2017/12/21,牛場、宮本) * --(MN PS V2:動作確認済み)--(2017/12/21,牛場、宮本) * --(MN PS V3:動作確認済み)--(2017/12/21,牛場、宮本) * --(MN Op''''''Lev Pitch: 実装したが要確認)-- -> (2018/1/23, 牛場) -> 2018/1/17予定 * --(MN Op''''''Lev Yaw: 実装したが要確認)-- -> (2018/1/23, 牛場) -> 2018/1/17予定 * --(温度計A:接続確認済み)--(2017/12/21,牛場) * --(温度計C:接続確認済み)--(2017/12/21,牛場) * --(温度計D:接続確認済み)--(2017/12/21,牛場) * --(温度計E:接続確認済み)--(2017/12/21,牛場) * --(温度計F:接続確認済み)--(2017/12/21,牛場) * 温度計G:出力不良、真空槽外配線が原因 (2018/1/XX,牛場、宮本) -> 原因はある程度特定できたがまだ未解決 * --(温度計H:接続確認済み)--(2017/12/21,牛場) |
* TM Op''''''Lev Pitch (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * TM Op''''''Lev Yaw (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * TM Op''''''Lev Length (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IM PS H1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IM PS H2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IM PS H3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IM PS V1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IM PS V2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IM PS V3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN PS H1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN PS H2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN PS H3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN PS V1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN PS V2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN PS V3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN Op''''''Lev Pitch (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN Op''''''Lev Yaw (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * 温度計A (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * 温度計C (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * 温度計D (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * 温度計E (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * 温度計F (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * 温度計G (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * 温度計H (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) |
Line 163: | Line 184: |
* --(TM アクチュエータ H1:動作確認済み)--(2017/12/11,牛場、宮本、長谷川、田中) * --(TM アクチュエータ H2:動作確認済み)--(2017/12/11,牛場、宮本、長谷川、田中) * --(TM アクチュエータ H3:動作確認済み)--(2017/12/11,牛場、宮本、長谷川、田中) * --(TM アクチュエータ H4:動作確認済み)--(2017/12/11,牛場、宮本、長谷川、田中) * --(IM アクチュエータ H1:動作確認済み)--(2017/12/15,牛場、宮本、長谷川) * --(IM アクチュエータ H2:動作確認済み)--(2017/12/15,牛場、宮本、長谷川) * --(IM アクチュエータ H3:動作確認済み)--(2017/12/15,牛場、宮本、長谷川) * --(IM アクチュエータ V1:動作確認済み)--(2017/12/15,牛場、宮本、長谷川) * --(IM アクチュエータ V2:動作確認済み)--(2017/12/15,牛場、宮本、長谷川) * --(IM アクチュエータ V3:動作確認済み)--(2017/12/15,牛場、宮本、長谷川) * --(MN アクチュエータ H1:動作確認済み)--(2017/12/15,牛場、宮本、長谷川) * --(MN アクチュエータ H2:動作確認済み)--(2017/12/15,牛場、宮本、長谷川) * --(MN アクチュエータ H3:動作確認済み)--(2017/12/15,牛場、宮本、長谷川) * --(MN アクチュエータ V1:動作確認済み)--(2017/12/15,牛場、宮本、長谷川) * --(MN アクチュエータ V2:動作確認済み)--(2017/12/15,牛場、宮本、長谷川) * --(MN アクチュエータ V3:動作確認済み)--(2017/12/15,牛場、宮本、長谷川) * --(SBS ダンピングコイル(V1-V4):接続確認済み)--(2017/12/??,牛場) * --(MN moving mass1:動作確認済み)--(2017/12/15,牛場、都丸) * --(MN moving mass2:動作確認済み)--(2017/12/15,牛場、都丸) * --(PF moving mass1:動作確認済み)--(2017/12/15,牛場、都丸) * --(PF moving mass2:動作確認済み)--(2017/12/15,牛場、都丸) |
* TM アクチュエータ H1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * TM アクチュエータ H2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * TM アクチュエータ H3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * TM アクチュエータ H4 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IM アクチュエータ H1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IM アクチュエータ H2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IM アクチュエータ H3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IM アクチュエータ V1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IM アクチュエータ V2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IM アクチュエータ V3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN アクチュエータ H1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN アクチュエータ H2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN アクチュエータ H3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN アクチュエータ V1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN アクチュエータ V2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN アクチュエータ V3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * SBS ダンピングコイル(V1-V4) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN moving mass1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN moving mass2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * PF moving mass1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * PF moving mass2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) |
Line 190: | Line 211: |
* --(MN, BFを用いたヒエラリカル制御 (TMのみなどではアクチュエータレンジ不足))-- (2018/1/14,牛場) | * MN, BFを用いたヒエラリカル制御 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) |
Check list for ETMX vacuum in spring, 2018
- Term: ~2018/4/20
Schedule
- 2018/3/26-4/6 : ETMX control test
- 2018/4/9-12 : Closing EXC
- 2018/4/5(Thur) 12:30 at fan hut.
- 2018/4/11(Wed) 12:30 at fan hut.
- 2018/4/12- : pump down
- 2018/4/18-20: leak check
Each item should have following format;
- item (checked date, checked person)
Once the item has been checked, it will be like:
item (2018/3/10, Somebody)
Alignment
Beam check at ETMX just before pump down(not possible with baffle PD through gate valve?) (2018/X/XX, Enomoto) -> Planned at 2018/4/11
Beam check at ETMY just before pump down (2018/X/XX, Enomoto) -> Planned at 2018/4/11
Beam check at REFL just before pump down (2018/X/XX, Enomoto) -> Planned at 2018/4/11
Preparation of monitors during pump down
Oplev monitor check for PRM (2018/X/XX Enomoto) -> Planned at 2018/4/11
Oplev monitor check for PR2 (2018/X/XX Enomoto) -> Planned at 2018/4/11
Oplev monitor check for PR3 (2018/X/XX Enomoto) -> Planned at 2018/4/11
Oplev monitor check for BS (2018/X/XX Enomoto) -> Planned at 2018/4/11
PD fot REFL (2018/4/XX Enomoto) -> Planned at 2018/4/11
GigE camera for IMMT1 (2018/X/XX Kokeyama) -> Planned at 2018/4/11
GigE camera for IMMT2 (2018/X/XX Kokeyama) -> Planned at 2018/4/11
GigE camera for PR2 (2018/X/XX Kokeyama) -> Planned at 2018/4/11
GigE camera for PR3 (2018/X/XX Kokeyama) -> Planned at 2018/4/11
GigE camera for BS (2018/X/XX Kokeyama) -> Planned at 2018/4/11
GigE camera for REFL (2018/X/XX Kokeyama) -> Planned at 2018/4/11
Tcam for ETMX (2018/X/XX Inoue) -> Planned at 2018/4/11
Tcam for ETMY (2018/X/XX Inoue) -> Planned at 2018/4/11
Tcam for ITMX (2018/4/5 Inoue)
Tcam for ITMY (2018/4/5 Inoue)
Illuminator for ETMX (2018/X/XX Inoue) -> Planned at 2018/4/11
Illuminator for ETMY) (2018/4/5 Inoue)
Vacuum gage for E end (2018/4/XX Inoue) -> Planned at 2018/4/16
Vacuum gage for X arm (2018/4/XX Inoue) -> Planned at 2018/4/16
Vacuum gage for Center area (2018/4/XX Uchiyama) -> Planned at 2018/4/16
真空槽の傾きをdial gaugeで測る。 (2018/4/XX Tomaru, Suzuki, Kimura) -> Planned at 2018/4/13
Xend 機器制御 for status monitors (2018/4/XX Tomaru, Suzuki, Kimura) -> Planned at 2018/4/5, 6
Vacuum gauge monitor at the control room at least one location (2018/X/XX Uchiyama, Kimura, Inoue, Miyoki) -> Planned at 2018/4/XX
その他追加項目
EQ stopの隙間のチェック5mm程度 (2018/X/XX, Ushiba, Tomaru) -> (2018/4/11 planed)
真空引き後、防振系の動作チェック (2018/X/XX, Enomoto) -> (2018/4/13 planed)
EXA ゲードバルブの動作チェック (2018/X/XX, Uchiyama) -> (2018/4/20 planed)
EXA ゲードバルブの開閉モニター to 機器制御 (今回は必須でないかもしれない) (2018/X/XX, Uchiyama) -> (2018/4/20 planed)
Type-A tower (高橋)
Fishing rodの動作チェック (2018/X/XX, Takahashi) -> (2018/4/6 planed, without camera)
--(Tuning of BF (2018/3/26, Takahashi)
Tuning of F3 (2018/3/27, Takahashi)
Tuning of TF (2018/3/27, Takahashi)
Tuning of position of BF damper (2018/3/28, Takahashi)
Centering IP (2018/3/27, Takahashi)
BF FRの動作確認 (2018/X/XX, Takahashi) -> (2018/X/XX planed)
BF yaw picomotorの動作確認 (2018/X/XX, Takahashi) -> (2018/X/XX planed)
トップ真空槽蓋閉め (2018/3/28, Takahashi)
トップ真空槽ボルト閉め (2018/X/XX, Kimura) -> (2018/4/10 planed)
クロス菅ボルト閉め (2018/X/XX, Kimura) -> (2018/4/10 planed)
IPの制御 (2018/4/XX, Okutomi) -> (2018/X/XX re-check)
BFのdamping制御 (2018/4/2, Okutomi) -> (2018/X/XX planed)
BF FRによるmirrorの高さ調整 (2018/4/5, Takahashi)
BF yaw picomotorによるmirrorのyaw調整 (2018/4/5, Ushiba)
事前にTypeA、Cryopayloadのアラインメント機構が動くかどうか確認する。 (2018/4/5, Ushiba)
BF温度計つなぎこみ (2018/X/XX, Takahashi, Ushiba) -> (2018/4/6 planed)
鏡板閉止 (Kimura)
8K および 80Kシールドにつける窓類の取り付け (2018/4/xx, Ushiba) -> (2018/4/11 just before closing EXC door)
輻射シールドのシャッター開確認 (2018/X/XX, Kimura) -> (2018/X/XX planed)
当該部のSuper Insulation(SI)取り外し確認 (2018/X/XX, Kimura) -> (2018/X/XX planed)
鏡板取付前の変換フランジ取付 (2018/X/XX, Kimura) -> (2018/4/9 planed)
鏡板取付後のビューポート取付 (2018/X/XX, Akutsu) -> (2018/4/12 planed)
Oplev用の島取付 (2018/X/XX, Akutsu) -> (2018/4/12 planed)
EXAチェンバー周り (Inoue)
フォトディテクターの取り外し (2018/X/XX, Yokozawa) -> (2018/3/27 planed)
GigEカメラの前の真空窓取り外しと取り付け (2018/X/XX, Inoue) -> (2018/4/5,6 planed)
EXV支持構造体のセット確認
- コーンベローズ用 3箇所 (2018/X/XX, 木村)
チェンバー本体用 3箇所 <- 真空引き前にフリーにする 今回はやらない
真空引き開始前後から冷却開始まで (木村)
- 真空フランジを開放し、再度閉止した箇所の確認(リーク試験箇所の確定に必要な情報です。)
- グループ毎の申告による
EXA 鏡板閉止 (2018/4/XX, Kimura) -> (2018/4/XX planed)
EXV top flange: VIS group (2018/X/XX, Takahashi) -> (2018/X/XX planed)
EXV ICF flange交換 ICF203/NW50 変換フランジ -> ICF203ブランクフランジ : VIS group (2018/3/28, Takahashi)
クロス菅鏡板2箇所: CRY group VIS group (2018/X/XX, Kimura) -> (2018/X/XX planed)
ICF253送風機接続ポート: CRY group (2018/X/XX, , Kimura) -> (2018/X/XX planed)
EXC鏡板2箇所: CRY group (2018/X/XX, Kimura) -> (2018/X/XX planed)
EXC ViewPort 4箇所?(鏡板2箇所、容器2箇所?):AOS (2018/X/XX, Akutsu, Ushiba) -> (2018/X/XX planed)
冷凍機NW-50フランジ交換 4箇所: CRY group (2018/X/XX, Kimura) -> (2018/X/XX planed)
EXA ICF152 2箇所: cal group (2018/4/5-6, Inoue) -> (2018/X/XX planed)
- グループ毎の申告による
- 温度・圧縮機のモニター
スタートさせる (2018/XX/XX, 都丸、麻生) -> (2018/X/XX planed)
温度・圧縮機のループテスト (2018/XX/XX, 都丸、麻生、木村) -> 冷却開始前までに予定
- 万が一遅れても冷却は遅らせない。ただし、一台すでに壊しているので、注意。
- 真空引き
真空計2台 ON (2018/X/XX, Kimura) -> (2018/X/XX planed)
粗挽きポンプスタート (2018/X/XX, Kimura) -> (2018/X/XX planed)
大まかなリークチェック (2018/X/XX, Kimura) -> (2018/X/XX planed)
ターボポンプ冷却水循環装置スタート (2018/X/XX, Kimura) -> (2018/X/XX planed)
ターボポンプスタート (2018/X/XX, Kimura) -> (2018/X/XX planed)
リーク試験 (2018/4/XX, Kimura) -> (2018/4/18 planed)
(リーク判定 < 1x10-10 Pa・m3/s)
EXA arm側ゲートバルブ動作チェック (2018/X/XX, Kimura) -> (2018/X/XX planed)
EXA arm側ゲートバルブOPEN (2018/X/XX, Kimura) -> (2018/X/XX planed)
メインレーザーを使ったバッフルPDの動作確認 (2018/X/XX, Enomoto) -> (2018/X/XX planed)
Cryo payload (都丸、牛場)
- リリース関係
PFのリリース(16箇所) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
MNのリリース(16箇所) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
MNRのリリース(16箇所) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
IMのリリース(6箇所) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
IMRのリリース(16箇所) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
TMのリリース(16箇所) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
TMRのリリース(15箇所) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
- センサーチェック
TM OpLev Pitch (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
TM OpLev Yaw (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
TM OpLev Length (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
IM PS H1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
IM PS H2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
IM PS H3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
IM PS V1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
IM PS V2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
IM PS V3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
MN PS H1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
MN PS H2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
MN PS H3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
MN PS V1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
MN PS V2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
MN PS V3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
MN OpLev Pitch (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
MN OpLev Yaw (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
温度計A (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
温度計C (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
温度計D (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
温度計E (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
温度計F (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
温度計G (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
温度計H (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
- アクチュエータチェック
TM アクチュエータ H1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
TM アクチュエータ H2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
TM アクチュエータ H3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
TM アクチュエータ H4 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
IM アクチュエータ H1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
IM アクチュエータ H2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
IM アクチュエータ H3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
IM アクチュエータ V1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
IM アクチュエータ V2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
IM アクチュエータ V3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
MN アクチュエータ H1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
MN アクチュエータ H2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
MN アクチュエータ H3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
MN アクチュエータ V1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
MN アクチュエータ V2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
MN アクチュエータ V3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
SBS ダンピングコイル(V1-V4) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
MN moving mass1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
MN moving mass2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
PF moving mass1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
PF moving mass2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
- ダンピング制御
MN, BFを用いたヒエラリカル制御 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)