Line 25: | Line 25: |
* Beam check at ETMX just before pump down(not possible with baffle PD through gate valve?) (2018/X/XX, Enomoto) -> Planned at 2018/4/11 | * --(Beam check at ETMX just before pump down(not possible with baffle PD through gate valve?))-- (2018/4/11 Enomoto) |
Line 32: | Line 32: |
* Oplev monitor check for PRM (2018/X/XX Enomoto) -> Planned at 2018/4/11 * Oplev monitor check for PR2 (2018/X/XX Enomoto) -> Planned at 2018/4/11 * Oplev monitor check for PR3 (2018/X/XX Enomoto) -> Planned at 2018/4/11 * Oplev monitor check for BS (2018/X/XX Enomoto) -> Planned at 2018/4/11 * PD fot REFL (2018/3/XX Enomoto) -> Planned at 2018/X/XX * GigE camera for IMMT1 (2018/X/XX Kokeyama) -> Planned at 2018/X/XX * GigE camera for IMMT2 (2018/X/XX Kokeyama) -> Planned at 2018/X/XX * GigE camera for PR2 (2018/X/XX Kokeyama) -> Planned at 2018/X/XX * GigE camera for PR3 (2018/X/XX Kokeyama) -> Planned at 2018/X/XX * GigE camera for BS (2018/X/XX Kokeyama) -> Planned at 2018/X/XX * Tcam for ETMX (2018/X/XX Inoue) -> Planned at 2018/3/XX * Tcam for ETMY (2018/X/XX Inoue) -> Planned at 2018/3/XX * Tcam for ITMX (2018/X/XX Inoue) -> Planned at 2018/3/XX * Tcam for ITMY (2018/X/XX Inoue) -> Planned at 2018/3/XX * Vacuum gage (2018/XX/XX Uchiyama) -> Planned at 2018/X/XX * 真空槽の傾きをdial gaugeで測る。 (2018/3/XX Tomaru, Suzuki, Kimura) -> Planned at 2018/3/XX * Xend 機器制御 (2018/3/XX Tomaru, Suzuki, Kimura) -> Planned at 2018/4/5, 6 * Vacuum gauge monitor at the control room at least one location (2018/X/XX Uchiyama, Kimura, Inoue, Miyoki) -> Planned at 2018/4/XX |
* --(Oplev monitor check for PRM)-- (2018/4/11 Enomoto) * --(Oplev monitor check for PR2)-- (2018/4/11 Enomoto) * --(Oplev monitor check for PR3)-- (2018/4/11 Enomoto) * --(Oplev monitor check for BS)-- (2018/4/11 Enomoto) * --(PD fot REFL)-- (2018/4/11 Enomoto) * GigE camera for IMMT1 (2018/X/XX Kokeyama) -> Planned at 2018/4/11 * GigE camera for IMMT2 (2018/X/XX Kokeyama) -> Planned at 2018/4/11 * GigE camera for PR2 (2018/X/XX Kokeyama) -> Planned at 2018/4/11 * GigE camera for PR3 (2018/X/XX Kokeyama) -> Planned at 2018/4/11 * GigE camera for BS (2018/X/XX Kokeyama) -> Planned at 2018/4/11 * GigE camera for REFL (2018/X/XX Kokeyama) -> Planned at 2018/4/11 * --(Tcam for ETMX)-- (2018/4/11 Inoue) * --(Tcam for ETMY)-- (2018/4/11 Inoue) * --(Tcam for ITMX)-- (2018/4/5 Inoue) * --(Tcam for ITMY)-- (2018/4/5 Inoue) * --(Illuminator for ETMX)-- (2018/4/5 Yokozawa) * --(Illuminator for ETMY)-- (2018/4/5 Inoue) * Vacuum gage for X end (2018/4/XX Inoue) -> Planned at 2018/4/17,18 * Vacuum gage for X arm (2018/4/XX Inoue) -> Planned at 2018/4/17,18 * Vacuum gage for Y arm (2018/4/XX Inoue) -> Planned at 2018/4/17,18 * Vacuum gage for IXA (2018/4/XX Inoue) -> Planned at 2018/4/17,18 * Vacuum gage for IYA (2018/4/XX Inoue) -> Planned at 2018/4/17,18 * Vacuum gage for PRM-PR2 (2018/4/XX Inoue) -> Planned at 2018/4/17,18 * 真空槽の傾きをdial gaugeで測る。 (2018/4/XX Tomaru, Suzuki, Kimura) -> Planned at 2018/4/13 * Xend 機器制御 for status monitors (2018/4/XX Tomaru, Suzuki, Kimura) -> Planned at 2018/4/13 * Vacuum gauge monitor at the control room at least one location (2018/X/XX Uchiyama, Kimura, Inoue, Miyoki) -> Planned at 2018/4/13 |
Line 56: | Line 66: |
* EQ stopの隙間のチェック5mm程度 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * 真空引き後、防振系の動作チェック (2018/X/XX, Enomoto) -> (2018/X/XX planed) * ゲードバルブの動作チェック (2018/X/XX, Uchiyama) -> (2018/X/XX planed) * ゲードバルブの開閉モニター (2018/X/XX, Uchiyama) -> (2018/X/XX planed) |
* Cryo payload EQ stopの隙間のチェック5mm程度 (2018/X/XX, Ushiba, Tomaru) -> (2018/4/11 planed) * 真空引き後、防振系の動作チェック (2018/X/XX, Enomoto) -> (2018/4/13 planed) * EXA ゲードバルブの動作チェック (2018/X/XX, Uchiyama) -> (2018/4/20 planed) * EXA ゲードバルブの開閉モニター to 機器制御 (今回は必須でないかもしれない) (2018/X/XX, Uchiyama) -> (2018/4/20 planed) * --(ダストウィットネスサンプル設置)-- (2018/4/11, Hirose) |
Line 62: | Line 73: |
* Tuning of BF (2018/3/26, Takahashi) * Tuning of F3 (2018/3/27, Takahashi) * Tuning of TF (2018/3/27, Takahashi) * Tuning of position of BF damper (2018/3/28, Takahashi) * Centering IP (2018/3/27, Takahashi) * BF FRの動作確認 (2018/X/XX, Takahashi) -> (2018/X/XX planed) * BF yaw picomotorの動作確認 (2018/X/XX, Takahashi) -> (2018/X/XX planed) * トップ真空槽蓋閉め (2018/3/28, Takahashi) * トップ真空槽ボルト閉め (2018/X/XX, Kimura) -> (2018/X/XX planed) * クロス菅ボルト閉め (2018/X/XX, Kimura) -> (2018/X/XX planed) * IPのDC制御 (2018/3/28, Okutomi) * BFのdamping制御 (2018/X/XX, Ushiba) -> (2018/X/XX planed) * BF FRによるmirrorの高さ調整 (2018/X/XX, Takahashi) -> (2018/X/XX planed) * BF yaw picomotorによるmirrorのyaw調整 (2018/X/XX, Takahashi) -> (2018/X/XX planed) * 事前にTypeA、Cryopayloadのアラインメント機構が動くかどうか確認する。 (2018/X/XX, ??) -> (2018/X/XX planed) * BF温度計つなぎこみ (2018/X/XX, Takahashi, Ushiba) -> (2018/X/XX planed) |
* --(Fishing rodの動作チェック)-- (2018/4/6, Takahashi) * --(Tuning of BF)-- (2018/3/26, Takahashi) * --(Tuning of F3)-- (2018/3/27, Takahashi) * --(Tuning of TF)-- (2018/3/27, Takahashi) * --(Tuning of position of BF damper)-- (2018/3/28, Takahashi) * --(Centering IP)-- (2018/3/27, Takahashi) * --(BF yaw picomotorの動作確認)-- (2018/4/11, Takahashi) * --(トップ真空槽蓋閉め)-- (2018/3/28, Takahashi) * --(トップ真空槽ボルト閉め)-- (2018/4/11, Kimura) * --(クロス菅ボルト閉め)-- (2018/4/11, Kimura) * IPの制御 (2018/4/XX, Okutomi) -> (2018/X/XX re-check) * --(BFのdamping制御)-- (2018/4/2, Okutomi) -> (2018/X/XX planed) * --(BF FRによるmirrorの高さ調整)-- (2018/4/5, Takahashi) * --(BF yaw picomotorによるmirrorのyaw調整)-- (2018/4/5, Ushiba) * --(事前にTypeA、Cryopayloadのアラインメント機構が動くかどうか確認する。)-- (2018/4/5, Ushiba) * --(BF温度計つなぎこみ)-- (2018/4/6, Takahashi, Ushiba) |
Line 80: | Line 92: |
* 8K および 80Kシールドにつける窓類の取り付け (2018/x/xx, xxxx) * 鏡板取付前の変換フランジ取付 (2018/X/XX, Kimura) -> (2018/X/XX planed) * 輻射シールドのシャッター開確認 (2018/X/XX, Kimura) -> (2018/X/XX planed) * 当該部のSuper Insulation(SI)取り外し確認 (2018/X/XX, Kimura) -> (2018/X/XX planed) * 鏡板取付後のビューポート取付 (2018/X/XX, Akutsu) -> (2018/X/XX planed) * Oplev用の島?取付 (2018/X/XX, Akutsu) -> (2018/X/XX planed) |
* --(8K および 80Kシールドにつける窓類の取り付け)-- (2018/4/11 Tomaru) * --(輻射シールドのシャッター開確認)-- (2018/4/5, Ushiba) * 当該部のSuper Insulation(SI)取り外し確認 (2018/X/XX, Kimura) -> (2018/4/11 planed) * --(鏡板取付前の変換フランジ取付)-- (2018/4/11 Kimura) * 鏡板取付後のビューポート取付 (2018/X/XX, Akutsu) -> (2018/4/12 planed) * Oplev用の島取付 (2018/X/XX, Akutsu) -> (2018/4/12 planed) |
Line 88: | Line 100: |
* フォトディテクターの取り外し (2018/X/XX, Yokozawa) -> (2018/3/27 planed) * GigEカメラの前の真空窓取り外しと取り付け (2018/X/XX, Inoue) -> (2018/4/5,6 planed) |
* --(フォトディテクターの取り外し)-- (2018/3/26, Yokozawa) * --(GigEカメラの前の真空窓取り外しと取り付け)-- (2018/4/9, Inoue) |
Line 92: | Line 104: |
1. コーンベローズ用 3箇所 (2018/X/XX, 木村) | 1. --(コーンベローズ脚ロックナットの固定確認 3箇所)-- (但し、手締め)(2018/4/12, 木村) |
Line 95: | Line 107: |
=== 真空引き開始前後から冷却開始まで (木村) === | === 真空引き開始前後 (木村) === |
Line 100: | Line 112: |
* EXA 鏡板閉止 (2018/4/XX, Kimura) -> (2018/4/XX planed) * EXV top flange: VIS group (2018/X/XX, Takahashi) -> (2018/X/XX planed) * EXV ICF flange交換 ICF203/NW50 変換フランジ -> ICF203ブランクフランジ : VIS group (2018/3/28, Takahashi) * クロス菅鏡板2箇所: CRY group VIS group (2018/X/XX, Kimura) -> (2018/X/XX planed) * ICF253送風機接続ポート: CRY group (2018/X/XX, , Kimura) -> (2018/X/XX planed) * EXC鏡板2箇所: CRY group (2018/X/XX, Kimura) -> (2018/X/XX planed) * EXC ViewPort 4箇所?(鏡板2箇所、容器2箇所?):AOS (2018/X/XX, Akutsu, Ushiba) -> (2018/X/XX planed) * 冷凍機NW-50フランジ交換 4箇所: CRY group (2018/X/XX, Kimura) -> (2018/X/XX planed) * EXA ICF152 2箇所: cal group (2018/4/5-6, Inoue) -> (2018/X/XX planed) * 温度・圧縮機のモニター |
* --(EXA 鏡板閉止)-- (2018/4/12, Kimura) * --(EXV top flange: VIS group)-- (2018/4/11, Kimura) * --(EXV ICF flange交換 ICF203/NW50 変換フランジ -> ICF203ブランクフランジ)-- : VIS group (2018/3/28, Takahashi) * --(クロス菅鏡板2箇所: CRY group, VIS group)-- (2018/4/11 Kimura) * --(ICF253送風機接続ポート: CRY group)-- (2018/4/11 Kimura) * --(EXC鏡板箇所: CRY group)-- (2018/4/11 Kimura) * EXC鏡板残り1箇所: CRY group (2018/X/XX, Kimura) -> (2018/4/11,12 planed) * --(EXC 鏡板View''''''Port 用変換フランジ1箇所:CRY group)-- (2018/4/11, Kimura) * EXC View''''''Port 3箇所(鏡板1箇所、--(容器2箇所)--):AOS (2018/X/XX, Akutsu) -> (2018/4/12 planed) * --(冷凍機NW-50フランジ交換 3箇所: CRY group)-- (2018/4/10, Kimura) * --(ICF152送風機接続ポート 2箇所: CRY group)-- (2018/4/10 Kimura) * --(EXA ICF152 2箇所: cal group)-- (2018/4/5-6, Inoue) * --(ICF253ガスケット交換(リークの疑い有り)1箇所: CRY group)-- (2018/4/11 Kimura) * --(EYC~クロス管挿しフランジ取り外しとフランジ再締結)-- (2018/3/12, Kimura) * --(EYA~EYC間レーザーハザード用挿しフランジ取り外しとフランジ再締結)-- (2018/3/12, Kimura) * 真空引き i. 真空計2台 ON (2018/X/XX, Kimura) -> (2018/4/13 planed) * 粗挽きポンプスタート (2018/X/XX, Kimura) -> (2018/4/13 planed) * 大まかなリークチェック (2018/X/XX, Kimura) -> (2018/4/13 planed) * ターボポンプ冷却水循環装置スタート (2018/X/XX, Kimura) -> (2018/4/16 planed) * ターボポンプスタート (2018/X/XX, Kimura) -> (2018/4/16 planed) * リーク試験 (2018/4/XX, Kimura) -> (2018/4/18-20 planed) * (リーク判定 < 1x10^-10 Pa・m^3/s) * ゲートバルブ動作試験 (2018/4/XX, Kimura) -> (2018/4/20 planed) * (温度・圧縮機のモニター) |
Line 113: | Line 144: |
* 万が一遅れても冷却は遅らせない。ただし、一台すでに壊しているので、注意。 * 真空引き i. 真空計2台 ON (2018/X/XX, Kimura) -> (2018/X/XX planed) * 粗挽きポンプスタート (2018/X/XX, Kimura) -> (2018/X/XX planed) * 大まかなリークチェック (2018/X/XX, Kimura) -> (2018/X/XX planed) * ターボポンプ冷却水循環装置スタート (2018/X/XX, Kimura) -> (2018/X/XX planed) * ターボポンプスタート (2018/X/XX, Kimura) -> (2018/X/XX planed) * リーク試験 (2018/4/XX, Kimura) -> (2018/4/18 planed) * (リーク判定 < 1x10^-10 Pa・m^3/s) * EXA arm側ゲートバルブ動作チェック (2018/X/XX, Kimura) -> (2018/X/XX planed) * EXA arm側ゲートバルブOPEN (2018/X/XX, Kimura) -> (2018/X/XX planed) * メインレーザーを使ったバッフルPDの動作確認 (2018/X/XX, Enomoto) -> (2018/X/XX planed) |
|
Line 132: | Line 149: |
* PFのリリース(16箇所) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MNのリリース(16箇所) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MNRのリリース(16箇所) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IMのリリース(6箇所) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IMRのリリース(16箇所) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * TMのリリース(16箇所) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * TMRのリリース(15箇所) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) |
* PFのリリース(16箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed) * MNのリリース(16箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed) * MNRのリリース(16箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed) * IMのリリース(6箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed) * IMRのリリース(16箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed) * TMのリリース(16箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed) * TMRのリリース(15箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed) |
Line 141: | Line 158: |
* TM Op''''''Lev Pitch (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * TM Op''''''Lev Yaw (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * TM Op''''''Lev Length (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IM PS H1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IM PS H2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IM PS H3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IM PS V1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IM PS V2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IM PS V3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN PS H1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN PS H2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN PS H3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN PS V1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN PS V2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN PS V3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN Op''''''Lev Pitch (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN Op''''''Lev Yaw (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) |
* --(TM Op''''''Lev Pitch)-- (2018/3/30, Ushiba, Tomaru) * --(TM Op''''''Lev Yaw)-- (2018/3/30, Ushiba, Tomaru) * TM Op''''''Lev Length (2018/X/XX, Ushiba, Tomaru) -> (2018/4/16 planed) * --(IM PS H1)-- (2018/4/5, Ushiba) * --(IM PS H2)-- (2018/4/5, Ushiba) * --(IM PS H3)-- (2018/4/5, Ushiba) * --(IM PS V1)-- (2018/4/5, Ushiba) * --(IM PS V2)-- (2018/4/5, Ushiba) * --(IM PS V3)-- (2018/4/5, Ushiba) * --(MN PS H1)-- (2018/4/5, Ushiba) * --(MN PS H2)-- (2018/4/6, Ushiba) * --(MN PS H3)-- (2018/4/5, Ushiba) * --(MN PS V1)-- (2018/4/5, Ushiba) * --(MN PS V2)-- (2018/4/5, Ushiba) * --(MN PS V3)-- (2018/4/5, Ushiba) * MN Op''''''Lev Pitch (2018/X/XX, Miyamoto) -> (2018/4/12 planed) * MN Op''''''Lev Yaw (2018/X/XX, Miyamoto) -> (2018/4/12 planed) |
Line 164: | Line 181: |
* 温度計B (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) | |
Line 173: | Line 191: |
* TM アクチュエータ H1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * TM アクチュエータ H2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * TM アクチュエータ H3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * TM アクチュエータ H4 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IM アクチュエータ H1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IM アクチュエータ H2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IM アクチュエータ H3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IM アクチュエータ V1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IM アクチュエータ V2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * IM アクチュエータ V3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN アクチュエータ H1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN アクチュエータ H2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN アクチュエータ H3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN アクチュエータ V1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN アクチュエータ V2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN アクチュエータ V3 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * SBS ダンピングコイル(V1-V4) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN moving mass1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * MN moving mass2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * PF moving mass1 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * PF moving mass2 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) |
* --(TM アクチュエータ H1)-- (2018/4/5, Ushiba) * --(TM アクチュエータ H2)-- (2018/4/5, Ushiba) * --(TM アクチュエータ H3)-- (2018/4/5, Ushiba) * --(TM アクチュエータ H4)-- (2018/4/5, Ushiba) * --(IM アクチュエータ H1)-- (2018/4/5, Ushiba) * --(IM アクチュエータ H2)-- (2018/4/5, Ushiba) * --(IM アクチュエータ H3)-- (2018/4/5, Ushiba) * --(IM アクチュエータ V1)-- (2018/4/5, Ushiba) * --(IM アクチュエータ V2)-- (2018/4/5, Ushiba) * --(IM アクチュエータ V3)-- (2018/4/5, Ushiba) * --(MN アクチュエータ H1)-- (2018/4/5, Ushiba) * --(MN アクチュエータ H2)-- (2018/4/5, Ushiba) * --(MN アクチュエータ H3)-- (2018/4/5, Ushiba) * --(MN アクチュエータ V1)-- (2018/4/5, Ushiba) * --(MN アクチュエータ V2)-- (2018/4/5, Ushiba) * --(MN アクチュエータ V3)-- (2018/4/5, Ushiba) * SBS ダンピングコイル(V1-V4) (2018/X/XX, Ushiba, Tomaru) 今回は無し * --(MN moving mass1)-- (2018/4/5, Ushiba) * --(MN moving mass2)-- (2018/4/5, Ushiba) * --(PF moving mass1)-- (2018/4/5, Ushiba) * --(PF moving mass2)-- (2018/4/5, Ushiba) |
Check list for ETMX vacuum in spring, 2018
- Term: ~2018/4/20
Schedule
- 2018/3/26-4/6 : ETMX control test
- 2018/4/9-12 : Closing EXC
- 2018/4/5(Thur) 12:30 at fan hut.
- 2018/4/11(Wed) 12:30 at fan hut.
- 2018/4/12- : pump down
- 2018/4/18-20: leak check
Each item should have following format;
- item (checked date, checked person)
Once the item has been checked, it will be like:
item (2018/3/10, Somebody)
Alignment
Beam check at ETMX just before pump down(not possible with baffle PD through gate valve?) (2018/4/11 Enomoto)
Beam check at ETMY just before pump down (2018/X/XX, Enomoto) -> Planned at 2018/4/11
Beam check at REFL just before pump down (2018/X/XX, Enomoto) -> Planned at 2018/4/11
Preparation of monitors during pump down
Oplev monitor check for PRM (2018/4/11 Enomoto)
Oplev monitor check for PR2 (2018/4/11 Enomoto)
Oplev monitor check for PR3 (2018/4/11 Enomoto)
Oplev monitor check for BS (2018/4/11 Enomoto)
PD fot REFL (2018/4/11 Enomoto)
GigE camera for IMMT1 (2018/X/XX Kokeyama) -> Planned at 2018/4/11
GigE camera for IMMT2 (2018/X/XX Kokeyama) -> Planned at 2018/4/11
GigE camera for PR2 (2018/X/XX Kokeyama) -> Planned at 2018/4/11
GigE camera for PR3 (2018/X/XX Kokeyama) -> Planned at 2018/4/11
GigE camera for BS (2018/X/XX Kokeyama) -> Planned at 2018/4/11
GigE camera for REFL (2018/X/XX Kokeyama) -> Planned at 2018/4/11
Tcam for ETMX (2018/4/11 Inoue)
Tcam for ETMY (2018/4/11 Inoue)
Tcam for ITMX (2018/4/5 Inoue)
Tcam for ITMY (2018/4/5 Inoue)
Illuminator for ETMX (2018/4/5 Yokozawa)
Illuminator for ETMY (2018/4/5 Inoue)
Vacuum gage for X end (2018/4/XX Inoue) -> Planned at 2018/4/17,18
Vacuum gage for X arm (2018/4/XX Inoue) -> Planned at 2018/4/17,18
Vacuum gage for Y arm (2018/4/XX Inoue) -> Planned at 2018/4/17,18
Vacuum gage for IXA (2018/4/XX Inoue) -> Planned at 2018/4/17,18
Vacuum gage for IYA (2018/4/XX Inoue) -> Planned at 2018/4/17,18
Vacuum gage for PRM-PR2 (2018/4/XX Inoue) -> Planned at 2018/4/17,18
真空槽の傾きをdial gaugeで測る。 (2018/4/XX Tomaru, Suzuki, Kimura) -> Planned at 2018/4/13
Xend 機器制御 for status monitors (2018/4/XX Tomaru, Suzuki, Kimura) -> Planned at 2018/4/13
Vacuum gauge monitor at the control room at least one location (2018/X/XX Uchiyama, Kimura, Inoue, Miyoki) -> Planned at 2018/4/13
その他追加項目
Cryo payload EQ stopの隙間のチェック5mm程度 (2018/X/XX, Ushiba, Tomaru) -> (2018/4/11 planed)
真空引き後、防振系の動作チェック (2018/X/XX, Enomoto) -> (2018/4/13 planed)
EXA ゲードバルブの動作チェック (2018/X/XX, Uchiyama) -> (2018/4/20 planed)
EXA ゲードバルブの開閉モニター to 機器制御 (今回は必須でないかもしれない) (2018/X/XX, Uchiyama) -> (2018/4/20 planed)
ダストウィットネスサンプル設置 (2018/4/11, Hirose)
Type-A tower (高橋)
Fishing rodの動作チェック (2018/4/6, Takahashi)
Tuning of BF (2018/3/26, Takahashi)
Tuning of F3 (2018/3/27, Takahashi)
Tuning of TF (2018/3/27, Takahashi)
Tuning of position of BF damper (2018/3/28, Takahashi)
Centering IP (2018/3/27, Takahashi)
BF yaw picomotorの動作確認 (2018/4/11, Takahashi)
トップ真空槽蓋閉め (2018/3/28, Takahashi)
トップ真空槽ボルト閉め (2018/4/11, Kimura)
クロス菅ボルト閉め (2018/4/11, Kimura)
IPの制御 (2018/4/XX, Okutomi) -> (2018/X/XX re-check)
BFのdamping制御 (2018/4/2, Okutomi) -> (2018/X/XX planed)
BF FRによるmirrorの高さ調整 (2018/4/5, Takahashi)
BF yaw picomotorによるmirrorのyaw調整 (2018/4/5, Ushiba)
事前にTypeA、Cryopayloadのアラインメント機構が動くかどうか確認する。 (2018/4/5, Ushiba)
BF温度計つなぎこみ (2018/4/6, Takahashi, Ushiba)
鏡板閉止 (Kimura)
8K および 80Kシールドにつける窓類の取り付け (2018/4/11 Tomaru)
輻射シールドのシャッター開確認 (2018/4/5, Ushiba)
当該部のSuper Insulation(SI)取り外し確認 (2018/X/XX, Kimura) -> (2018/4/11 planed)
鏡板取付前の変換フランジ取付 (2018/4/11 Kimura)
鏡板取付後のビューポート取付 (2018/X/XX, Akutsu) -> (2018/4/12 planed)
Oplev用の島取付 (2018/X/XX, Akutsu) -> (2018/4/12 planed)
EXAチェンバー周り (Inoue)
フォトディテクターの取り外し (2018/3/26, Yokozawa)
GigEカメラの前の真空窓取り外しと取り付け (2018/4/9, Inoue)
EXV支持構造体のセット確認
コーンベローズ脚ロックナットの固定確認 3箇所 (但し、手締め)(2018/4/12, 木村)
チェンバー本体用 3箇所 <- 真空引き前にフリーにする 今回はやらない
真空引き開始前後 (木村)
- 真空フランジを開放し、再度閉止した箇所の確認(リーク試験箇所の確定に必要な情報です。)
- グループ毎の申告による
EXA 鏡板閉止 (2018/4/12, Kimura)
EXV top flange: VIS group (2018/4/11, Kimura)
EXV ICF flange交換 ICF203/NW50 変換フランジ -> ICF203ブランクフランジ : VIS group (2018/3/28, Takahashi)
クロス菅鏡板2箇所: CRY group, VIS group (2018/4/11 Kimura)
ICF253送風機接続ポート: CRY group (2018/4/11 Kimura)
EXC鏡板箇所: CRY group (2018/4/11 Kimura)
EXC鏡板残り1箇所: CRY group (2018/X/XX, Kimura) -> (2018/4/11,12 planed)
EXC 鏡板ViewPort 用変換フランジ1箇所:CRY group (2018/4/11, Kimura)
EXC ViewPort 3箇所(鏡板1箇所、容器2箇所):AOS (2018/X/XX, Akutsu) -> (2018/4/12 planed)
冷凍機NW-50フランジ交換 3箇所: CRY group (2018/4/10, Kimura)
ICF152送風機接続ポート 2箇所: CRY group (2018/4/10 Kimura)
EXA ICF152 2箇所: cal group (2018/4/5-6, Inoue)
ICF253ガスケット交換(リークの疑い有り)1箇所: CRY group (2018/4/11 Kimura)
EYC~クロス管挿しフランジ取り外しとフランジ再締結 (2018/3/12, Kimura)
EYA~EYC間レーザーハザード用挿しフランジ取り外しとフランジ再締結 (2018/3/12, Kimura)
- グループ毎の申告による
- 真空引き
真空計2台 ON (2018/X/XX, Kimura) -> (2018/4/13 planed)
粗挽きポンプスタート (2018/X/XX, Kimura) -> (2018/4/13 planed)
大まかなリークチェック (2018/X/XX, Kimura) -> (2018/4/13 planed)
ターボポンプ冷却水循環装置スタート (2018/X/XX, Kimura) -> (2018/4/16 planed)
ターボポンプスタート (2018/X/XX, Kimura) -> (2018/4/16 planed)
リーク試験 (2018/4/XX, Kimura) -> (2018/4/18-20 planed)
(リーク判定 < 1x10-10 Pa・m3/s)
ゲートバルブ動作試験 (2018/4/XX, Kimura) -> (2018/4/20 planed)
- (温度・圧縮機のモニター)
スタートさせる (2018/XX/XX, 都丸、麻生) -> (2018/X/XX planed)
温度・圧縮機のループテスト (2018/XX/XX, 都丸、麻生、木村) -> 冷却開始前までに予定
Cryo payload (都丸、牛場)
- リリース関係
PFのリリース(16箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed)
MNのリリース(16箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed)
MNRのリリース(16箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed)
IMのリリース(6箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed)
IMRのリリース(16箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed)
TMのリリース(16箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed)
TMRのリリース(15箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed)
- センサーチェック
TM OpLev Pitch (2018/3/30, Ushiba, Tomaru)
TM OpLev Yaw (2018/3/30, Ushiba, Tomaru)
TM OpLev Length (2018/X/XX, Ushiba, Tomaru) -> (2018/4/16 planed)
IM PS H1 (2018/4/5, Ushiba)
IM PS H2 (2018/4/5, Ushiba)
IM PS H3 (2018/4/5, Ushiba)
IM PS V1 (2018/4/5, Ushiba)
IM PS V2 (2018/4/5, Ushiba)
IM PS V3 (2018/4/5, Ushiba)
MN PS H1 (2018/4/5, Ushiba)
MN PS H2 (2018/4/6, Ushiba)
MN PS H3 (2018/4/5, Ushiba)
MN PS V1 (2018/4/5, Ushiba)
MN PS V2 (2018/4/5, Ushiba)
MN PS V3 (2018/4/5, Ushiba)
MN OpLev Pitch (2018/X/XX, Miyamoto) -> (2018/4/12 planed)
MN OpLev Yaw (2018/X/XX, Miyamoto) -> (2018/4/12 planed)
温度計A (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
温度計B (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
温度計C (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
温度計D (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
温度計E (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
温度計F (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
温度計G (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
温度計H (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
- アクチュエータチェック
TM アクチュエータ H1 (2018/4/5, Ushiba)
TM アクチュエータ H2 (2018/4/5, Ushiba)
TM アクチュエータ H3 (2018/4/5, Ushiba)
TM アクチュエータ H4 (2018/4/5, Ushiba)
IM アクチュエータ H1 (2018/4/5, Ushiba)
IM アクチュエータ H2 (2018/4/5, Ushiba)
IM アクチュエータ H3 (2018/4/5, Ushiba)
IM アクチュエータ V1 (2018/4/5, Ushiba)
IM アクチュエータ V2 (2018/4/5, Ushiba)
IM アクチュエータ V3 (2018/4/5, Ushiba)
MN アクチュエータ H1 (2018/4/5, Ushiba)
MN アクチュエータ H2 (2018/4/5, Ushiba)
MN アクチュエータ H3 (2018/4/5, Ushiba)
MN アクチュエータ V1 (2018/4/5, Ushiba)
MN アクチュエータ V2 (2018/4/5, Ushiba)
MN アクチュエータ V3 (2018/4/5, Ushiba)
- SBS ダンピングコイル(V1-V4) (2018/X/XX, Ushiba, Tomaru) 今回は無し
MN moving mass1 (2018/4/5, Ushiba)
MN moving mass2 (2018/4/5, Ushiba)
PF moving mass1 (2018/4/5, Ushiba)
PF moving mass2 (2018/4/5, Ushiba)
- ダンピング制御
MN, BFを用いたヒエラリカル制御 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)