Differences between revisions 2 and 3
Revision 2 as of 2017-11-14 10:18:12
Size: 606
Comment:
Revision 3 as of 2017-11-14 10:19:05
Size: 569
Comment:
Deletions are marked like this. Additions are marked like this.
Line 2: Line 2:
 * Target
Line 6: Line 5:
 * Alignment of ETMy

=== Target ===
=== Tasks ===
Line 21: Line 18:
=== Tasks ===
Line 22: Line 20:
=== Target ===

Stage 1

  • Alignment up to BS

Stage 2

Tasks

  • Align ETMy to IFI (MIF, DGS, VIS, CRY, IOO) with damping
  • Lead MI-REFL beam outside the chamber (MIF, IOO)
  • Install and align MI-REFL output optics using the beam reflected by ETMy (MIF)

Preparation

  • Oplev
  • Actuator
  • EYCのTypeAとPayload接続完了

Stage 3

Tasks

  • Alignment of ETMx
  • Locking of MI with Cryogenic ETMy with Calibrated sensitivity curve

Stage 4

  • Locking of MI in vacuum with cryogenic ETMx/y with data stored

KAGRA/Commissioning/Phase1/Task (last edited 2018-05-24 11:21:22 by OsamuMiyakawa)