Differences between revisions 1 and 82 (spanning 81 versions)
Revision 1 as of 2018-08-08 16:31:07
Size: 10601
Comment:
Revision 82 as of 2018-08-16 13:45:54
Size: 9626
Comment:
Deletions are marked like this. Additions are marked like this.
Line 1: Line 1:
== Check list for ITMX vacuum in August, 2018 == == Check list for ITMX vacuum in Summer of 2018 ==
Line 3: Line 3:
 * Term: ~2018/8/27  * Term: ~2018/9
Line 8: Line 9:
 * 2018/8/27 : Closing EXC
 * 2018/8/??- : pump down
 * 2018/8/??: leak check
 * 2018/8/20の週: アルミホイルを外す。鏡の測定の位置確認、WABの設定。
 * 2018/8/21: IPリリース、調整
 * 2018/8/27(Mon) : Closing IXC、同日cryostatの掃除をする。
 * 2018/8/30(Wed) : Closing IXA by Mira-Pro
 * 2018/8/30(Thur)夕方- : pump down、30日にポンプ一台で粗挽き、31日金曜日に本引き
 * 2018/9/3-5: leak check
 * 2018/9/5-7: φ800のフランジ開け
 * 9/10: 停電対策で真空関係の対応
Line 21: Line 27:
=== Preparation of monitors during pump down ===
Line 22: Line 29:
=== Alignment ===
 * Beam check at ETMX just before pump down(not possible with baffle PD through gate valve?) (2018/4/11 Enomoto)
 * Beam check at ETMY just before pump down (2018/4/13, Enomoto)
 * Beam check at REFL just before pump down (2018/4/13, Enomoto)
 * Tcam for ITMX (2018/8/?? Yokozawa) -> (2018/8/22 planed)
 * Vacuum gage for KAGRA (2018/8/XX Tomaru) -> (2018/8/XX planed)

 * 真空槽の傾きをdial gaugeで測る。 (2018/8/XX Kimura) -> (2018/8/27~ planed, measured from 8/30~)
 * ITMX 機器制御 for status monitors (2018/8/XX Tomaru) -> (2018/8/XX planed)
 * Vacuum gauge monitor at the control room (2018/8/XX Tomaru) -> (2018/8/XX planed)
Line 28: Line 37:
=== Preparation of monitors during pump down === === 真空引き後、追加項目 ===
Line 30: Line 39:
 * --(Oplev monitor check for PRM)-- (2018/4/11 Enomoto)
 * --(Oplev monitor check for PR2)-- (2018/4/11 Enomoto)
 * --(Oplev monitor check for PR3)-- (2018/4/11 Enomoto)
 * --(Oplev monitor check for BS)-- (2018/4/11 Enomoto)
 * --(PD fot REFL)-- (2018/4/11 Enomoto)

 * --(GigE camera for IMMT1)-- (2018/4/13 Enomoto)
 * --(GigE camera for IMMT2)-- (2018/4/13 Enomoto)
 * --(GigE camera for PR2)-- (2018/4/13 Enomoto)
 * --(GigE camera for PR3)-- (2018/4/13 Enomoto)
 * --(GigE camera for BS)-- (2018/4/13 Enomoto)
 * --(GigE camera for REFL)-- (2018/4/13 Enomoto)

 * --(Tcam for ETMX)-- (2018/4/11 Inoue)
 * --(Tcam for ETMY)-- (2018/4/11 Inoue)
 * --(Tcam for ITMX)-- (2018/4/5 Inoue)
 * --(Tcam for ITMY)-- (2018/4/5 Inoue)
 * --(Illuminator for ETMX)-- (2018/4/5 Yokozawa)
 * --(Illuminator for ETMY)-- (2018/4/5 Inoue)

 * Vacuum gage for X end (2018/4/XX Inoue) -> Planned at 2018/4/17,18
 * Vacuum gage for X arm (2018/4/XX Inoue) -> Planned at 2018/4/17,18
 * Vacuum gage for Y arm (2018/4/XX Inoue) -> Planned at 2018/4/17,18
 * Vacuum gage for IXA (2018/4/XX Inoue) -> Planned at 2018/4/17,18
 * Vacuum gage for IYA (2018/4/XX Inoue) -> Planned at 2018/4/17,18
 * Vacuum gage for PRM-PR2 (2018/4/XX Inoue) -> Planned at 2018/4/17,18

 * 真空槽の傾きをdial gaugeで測る。 (2018/4/XX Tomaru, Suzuki, Kimura) -> Planned at 2018/4/13
 * Xend 機器制御 for status monitors (2018/4/XX Tomaru, Suzuki, Kimura) -> Planned at 2018/4/13
 * --(Vacuum gauge monitor at the control room at least one location)-- (2018/4/12 Uchiyama, Kimura, Inoue, Miyoki)
 * 真空引き後、防振系の動作チェック (2018/X/XX, Fujii) -> (2018/8/XX planed)
 * Xarmコミッショニング時、IXA ゲードバルブの動作チェック (2018/X/XX, Kimura) -> (2018/9/XX planed)
 * Xarmコミッショニング時、BS ゲードバルブの動作チェック (2018/X/XX, Kimura) -> (2018/9/XX planed)
Line 62: Line 44:
=== その他追加項目 === === Type-A tower (高橋) ===
Line 64: Line 46:
 * --(Cryo payload EQ stopの隙間のチェック5mm程度)-- (2018/4/12, Tomaru)
 * 真空引き後、防振系の動作チェック (2018/X/XX, Enomoto) -> (2018/4/13 planed)
 * EXA ゲードバルブの動作チェック (2018/X/XX, Uchiyama) -> (2018/4/20 planed)
 * EXA ゲードバルブの開閉モニター to 機器制御 (今回は必須でないかもしれない) (2018/X/XX, Uchiyama) -> (2018/4/20 planed)
 * --(ダストウィットネスサンプル設置)-- (2018/4/11, Hirose)

=== Type-A tower (高橋) ===
 * --(Fishing rodの動作チェック)-- (2018/4/6, Takahashi)
 * --(Tuning of BF)-- (2018/3/26, Takahashi)
 * --(Tuning of F3)-- (2018/3/27, Takahashi)
 * --(Tuning of TF)-- (2018/3/27, Takahashi)
 * --(Tuning of position of BF damper)-- (2018/3/28, Takahashi)
 * --(Centering IP)-- (2018/3/27, Takahashi)
 * --(BF yaw picomotorの動作確認)-- (2018/4/11, Takahashi)
 * --(トップ真空槽蓋閉め)-- (2018/3/28, Takahashi)
 * --(トップ真空槽ボルト閉め)-- (2018/4/11, Kimura)
 * --(クロス菅ボルト閉め)-- (2018/4/11, Kimura)
 * --(IPの制御)-- (2018/4/13, Takahashi)
 * --(BFのdamping制御)-- (2018/4/2, Okutomi) -> (2018/X/XX planed)
 * --(BF FRによるmirrorの高さ調整)-- (2018/4/5, Takahashi)
 * --(BF yaw picomotorによるmirrorのyaw調整)-- (2018/4/5, Ushiba)
 * --(事前にTypeA、Cryopayloadのアラインメント機構が動くかどうか確認する。)-- (2018/4/5, Ushiba)
 * --(BF温度計つなぎこみ)-- (2018/4/6, Takahashi, Ushiba)
 * IPリリース、調整 (2018/X/XX, Okutomi) -> (2018/8/21 planed)
 * Fishing rodの動作チェック (2018/X/XX, Takahashi)
 * Tuning of BF (2018/X/XX, Takahashi)
 * Tuning of F3 (2018/X/XX, Takahashi)
 * Tuning of TF (2018/X/XX, Takahashi)
 * Tuning of position of BF damper (2018/X/XX, Takahashi)
 * Centering IP (2018/X/XX, Takahashi)
 * BF yaw picomotorの動作確認 (2018/X/XX, Takahashi)
 * トップ真空槽蓋閉め (2018/X/XX, Takahashi) -> (2018/8/30 planed by Mira-pro)
 * トップ真空槽ボルト閉め (2018/X/XX, Takahashi) -> (2018/8/30 planed by Mira-pro)
 * クロス菅ボルト閉め (2018/X/XX, Takahashi) -> (2018/8/30 planed by Mira-pro)
 * IPの制御 (2018/X/XX, Takahashi)
 * BFのdamping制御 (2018/X/XX, Okutomi) -> (2018/X/XX planed)
 * BF FRによるmirrorの高さ調整 (2018/X/XX, Takahashi) -> (2018/8/?? planed)
 * BF yaw picomotorによるmirrorのyaw調整 (2018/X/XX, Ushiba) -> (2018/8/?? planed)
 * 事前にTypeA、Cryopayloadのアラインメント機構が動くかどうか確認する。 (2018/X/XX, Ushiba)
 * BF温度計つなぎこみ (2018/X/XX, Takahashi, Ushiba) -> (2018/8/?? planed)
Line 90: Line 66:
 * --(8K および 80Kシールドにつける窓類の取り付け)-- (2018/4/11 Tomaru)
 * --(輻射シールドのシャッター開確認)-- (2018/4/5, Ushiba)
 * --(当該部のSuper Insulation(SI)取り外し確認)-- (2018/4/12, Kimura)
 * --(鏡板取付前の変換フランジ取付)-- (2018/4/11 Kimura)
 * --(鏡板取付後のビューポート取付)-- (2018/4/12, Akutsu)
 * Oplev用の島取付 (2018/X/XX, Akutsu) -> (2018/4/12 planed)
 * 8K および 80Kシールドにつける窓類の取り付け (2018/X/XX Kimura) -> (2018/8/27,28 planed)
 * 輻射シールドのシャッター開確認 (2018/X/XX Kimura) -> (2018/8/27,28 planed)
 * 当該部のSuper Insulation(SI)取り外し確認 (2018/X/XX Kimura) -> (2018/8/27,28 planed)
 * --(鏡板取付前の変換フランジ取付)-- (2018/8/10 Kimura)
 * 鏡板取付後のビューポート取付 (2018/X/XX, Ushiba) -> (2018/8/27,28 planed)
 * Oplev用の島取付 (2018/X/XX, Ushiba) -> (2018/8/27,28 planed)
 * Q massの取り付け (2018/X/XX Kimura) -> (2018/8/27-31 planed)
Line 97: Line 74:
=== EXAチェンバー周り (Inoue) ===
 * --(フォトディテクターの取り外し)-- (2018/3/26, Yokozawa)
 * --(GigEカメラの前の真空窓取り外しと取り付け)-- (2018/4/9, Inoue)
=== IXV支持構造体のセット確認 ===
 1. コーンベローズ脚ロックナットの固定確認 3箇所 (但し、手締め)(2018/X/XX, Kimura) -> (2018/8/30 planed)
 * チェンバー本体用 3箇所 <- 今回は固定のまま (2018/X/XX, Kimura) -> (2018/8/30 planed)
Line 101: Line 78:
=== EXV支持構造体のセット確認 ===
 1. --(コーンベローズ脚ロックナットの固定確認 3箇所)-- (但し、手締め)(2018/4/12, 木村)
 * --(チェンバー本体用 3箇所 <- 真空引き前にフリーにする)-- 今回はやらない
=== WAB (阿久津)at IXC ===
 * Type-A+cryopayloadがbalance地点に調整されしだい、finalize(2018/X/XX, Akutsu)-> (2018/8/22、23)
  * finalize前に、
   * Type-A+cryopayloadがbalance地点に調整されているか
   * Assembly frameが動く状態になっているか
  * やる作業としては
   * WABを定位置に固定、WABにヒートリンクなどを取り付ける
 * cooling bar1本設置 (2018/X/XX, Tomaru) -> (2018/8/27 planed)
 * Cooling barからHeat link取り付け (2018/X/XX, Tomaru) -> (2018/8/27 planed)

=== NAB(阿久津)at IXA ===
 * --(NABがリリースされているか?(2018/08/09, Akutsu))--
 * NAB/Tcam frameについている白テープを全て剥がしたか? (Yokozawa、Akutsu) -> (2018/8/20 planed)
 * NABのQ-factor測定の状況は確認したか (2018/08/XX, Akutsu) -> (2018/8/20-29 planed)
Line 110: Line 98:
   * --(EXA 鏡板閉止)-- (2018/4/12, Kimura)
   * --(EXV top flange: VIS group)-- (2018/4/11, Kimura)
   * --(EXV ICF flange交換 ICF203/NW50 変換フランジ -> ICF203ブランクフランジ)-- : VIS group (2018/3/28, Takahashi)
   * --(クロス菅鏡板2箇所: CRY group, VIS group)-- (2018/4/11 Kimura)
   * --(ICF253送風機接続ポート: CRY group)-- (2018/4/11 Kimura)
   * --(EXC鏡板箇所: CRY group)-- (2018/4/11 Kimura)
   * --(EXC鏡板残り1箇所: CRY group)-- (2018/4/12, Kimura) <- 鏡板閉止完了
   * --(EXC 鏡板View''''''Port 用変換フランジ1箇所:CRY group)-- (2018/4/11, Kimura)
   * --(EXC View''''''Port 3箇所(鏡板1箇所、容器2箇所): AOS)-- (2018/4/12, Akutsu)
   * --(冷凍機NW-50フランジ交換 3箇所: CRY group)-- (2018/4/10, Kimura)
   * --(ICF152送風機接続ポート 2箇所: CRY group)-- (2018/4/10 Kimura)
   * --(EXA ICF152 2箇所: cal group)-- (2018/4/5-6, Inoue)
   * --(ICF253ガスケット交換(リークの疑い有り)1箇所: CRY group)-- (2018/4/11 Kimura)
   * --(EYC~クロス管挿しフランジ取り外しとフランジ再締結)-- (2018/3/12, Kimura)
   * --(EYA~EYC間レーザーハザード用挿しフランジ取り外しとフランジ再締結)-- (2018/3/12, Kimura)
   * --(EYAのEYC側ベローズ締結部(寺田さん、内山さんによるビーム位置測定で使用))-- (2018/3/12, Kimura)
   * IXA Top閉止 (2018/X/XX, Kimura) -> (2018/8/30 planed)
   * IXA 鏡板閉止 (2018/X/XX, Kimura) -> (2018/8/30 planed)
   * IXV top flange: VIS group (2018/X/XX, Kimura) -> (2018/8/30 planed)
   * クロス菅鏡板2箇所: CRY group, VIS group (2018/X/XX Kimura) -> (2018/8/30 planed)
   * ICF152送風機接続ポート(空気導入用ポート取り付け): CRY group (2018/X/XX Kimura) -> (2018/8/30 planed)
   * IXC鏡板箇所: CRY group (2018/X/XX Kimura) -> (2018/8/27、28 planed)
   * --(IXC 鏡板View''''''Port 用変換フランジ1箇所:CRY group)-- (2018/8/10, Kimura)
   * IXC View''''''Port 3箇所(鏡板1箇所、容器2箇所): AOS (2018/X/XX, Ushiba) -> (2018/8/28 planed)
   * --(冷凍機NW-50フランジ交換 3箇所: CRY group)-- (2018/6, Kimura)
   * IXA ICF152 2箇所: cal group (2018/X/XX, Yokozawa, 要確認)
   * --(IXC~クロス管挿しフランジ取り外しとフランジ再締結)-- (2018/6, Kimura)
   * --(IXA~IXC間レーザーハザード用挿しフランジ取り外しとフランジ再締結)-- (2018/3/12, Kimura)
   * --(IXAのIXC側ベローズ締結部(寺田さん、内山さんによるビーム位置測定で使用) )-- (2018/3/12, Kimura)
   * --(IXAの上ぶた (NAB/TCam/BafflePDs) )--
   * --(IXAの両サイドフランジ (NAB/TCam/BafflePDs) )--
   * --(IXAのICF70 viewport。3km腕側で、-Y側。 (NAB))-- (2018/6, Akutsu)
   * --(IXAの上側のICF203部分。コネクタつきのフランジに交換した (BafflePD) )-- (2018/8/7, Enomoto)
Line 129: Line 118:
  i. --(真空計2台 ON)-- (2018/4/13, Kimura)
  * --(粗挽きポンプスタート)-- (2018/4/13, Kimura)
  * 大まかなリークチェック (2018/X/XX, Kimura) -> (2018/4/13 planed)
  * --(ターボポンプ冷却水循環装置スタート)-- (2018/4/13, Kimura)
  * ターボポンプスタート (2018/X/XX, Kimura) -> (2018/4/16 planed)
  i. 真空計2台 ON (2018/X/XX, Kimura)
  * 粗挽きポンプスタート (2018/X/XX, Kimura)
  * 大まかなリークチェック (2018/X/XX, Kimura)
  * ターボポンプ冷却水循環装置スタート (2018/X/XX, Kimura)
  * ターボポンプスタート (2018/X/XX, Kimura)
Line 135: Line 124:
 * リーク試験 (2018/4/XX, Kimura) -> (2018/4/18-20 planed)  * リーク試験 (2018/X/XX, Kimura)
Line 138: Line 127:
 * ゲートバルブ動作試験 (2018/4/XX, Kimura) -> (2018/4/20 planed)  * ゲートバルブ動作試験 (2018/8/XX, Kimura) <- 今回は無し
Line 141: Line 130:
 * (温度・圧縮機のモニター)  * (温度・圧縮機のモニター) <- 今回は無し
Line 148: Line 137:
 * リリース関係
  * --(PFのリリース(16箇所))-- (2018/4/12, Tomaru)
  * --(MNのリリース(16箇所))-- (2018/4/12, Tomaru)
  * --(MNRのリリース(16箇所))-- (2018/4/12, Tomaru)
  * --(IMのリリース(6箇所))-- (2018/4/12, Tomaru)
  * --(IMRのリリース(16箇所))-- (2018/4/12, Tomaru)
  * --(TMのリリース(16箇所))-- (2018/4/12, Tomaru)
  * --(TMRのリリース(15箇所))-- (2018/4/12, Tomaru)
 * Cryo payload EQ stopの隙間のチェック5mm程度 (2018/X/XX, Ushiba)
Line 158: Line 139:
  * --(TM Op''''''Lev Pitch)-- (2018/3/30, Ushiba, Tomaru)
  * --(TM Op''''''Lev Yaw)-- (2018/3/30, Ushiba, Tomaru)
  * TM Op''''''Lev Length (2018/X/XX, Ushiba, Tomaru) -> (2018/4/16 planed)
  * TM Op''''''Lev Pitch (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
  * TM Op''''''Lev Yaw (2018/X/XX, Ushiba, Tomaru)
  * TM Op''''''Lev Length (2018/X/XX, Ushiba, Tomaru)
Line 163: Line 144:
  * --(IM PS H1)-- (2018/4/5, Ushiba)
  * --(IM PS H2)-- (2018/4/5, Ushiba)
  * --(IM PS H3)-- (2018/4/5, Ushiba)
  * --(IM PS V1)-- (2018/4/5, Ushiba)
  * --(IM PS V2)-- (2018/4/5, Ushiba)
  * --(IM PS V3)-- (2018/4/5, Ushiba)
  * IM PS H1 (2018/X/XX, Ushiba) -> (2018/X/XX planed)
  * IM PS H2 (2018/X/XX, Ushiba)
  * IM PS H3 (2018/X/XX, Ushiba)
  * IM PS V1 (2018/X/XX, Ushiba)
  * IM PS V2 (2018/X/XX, Ushiba)
  * IM PS V3 (2018/X/XX, Ushiba)
Line 170: Line 151:
  * --(MN PS H1)-- (2018/4/5, Ushiba)
  * --(MN PS H2)-- (2018/4/6, Ushiba)
  * --(MN PS H3)-- (2018/4/5, Ushiba)
  * --(MN PS V1)-- (2018/4/5, Ushiba)
  * --(MN PS V2)-- (2018/4/5, Ushiba)
  * --(MN PS V3)-- (2018/4/5, Ushiba)
  * MN PS H1 (2018/X/XX, Ushiba)
  * MN PS H2 (2018/X/XX, Ushiba)
  * MN PS H3 (2018/X/XX, Ushiba)
  * MN PS V1 (2018/X/XX, Ushiba)
  * MN PS V2 (2018/X/XX, Ushiba)
  * MN PS V3 (2018/X/XX, Ushiba)
Line 177: Line 158:
  * MN Op''''''Lev Pitch (2018/X/XX, Miyamoto) -> (2018/4/12 planed)
  * MN Op''''''Lev Yaw (2018/X/XX, Miyamoto) -> (2018/4/12 planed)
  * MN Op''''''Lev Pitch (2018/X/XX, Miyamoto) -> (2018/X/XX planed)
  * MN Op''''''Lev Yaw (2018/X/XX, Miyamoto)
Line 181: Line 162:
  * 温度計B (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
  * 温度計C (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
  * 温度計D (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
  * 温度計E (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
  * 温度計F (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
  * 温度計G (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
  * 温度計H (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
  * 温度計B (2018/X/XX, Ushiba, Tomaru)
  * 温度計C (2018/X/XX, Ushiba, Tomaru)
  * 温度計D (2018/X/XX, Ushiba, Tomaru)
  * 温度計E (2018/X/XX, Ushiba, Tomaru)
  * 温度計F (2018/X/XX, Ushiba, Tomaru)
  * 温度計G (2018/X/XX, Ushiba, Tomaru)
  * 温度計H (2018/X/XX, Ushiba, Tomaru)
Line 191: Line 172:
  * --(TM アクチュエータ H1)-- (2018/4/5, Ushiba)
  * --(TM アクチュエータ H2)-- (2018/4/5, Ushiba)
  * --(TM アクチュエータ H3)-- (2018/4/5, Ushiba)
  * --(
TM アクチュエータ H4)-- (2018/4/5, Ushiba)
  * TM アクチュエータ H1 (2018/X/XX, Ushiba) -> (2018/X/XX planed)
  * TM アクチュエータ H2 (2018/X/XX
, Ushiba)
  * TM アクチュエータ H3 (2018/X/XX, Ushiba)
  * TM アクチュエータ H4 (2018/X/XX, Ushiba)
Line 196: Line 177:
  * --(IM アクチュエータ H1)-- (2018/4/5, Ushiba)
  * --(IM アクチュエータ H2)-- (2018/4/5, Ushiba)
  * --(IM アクチュエータ H3)-- (2018/4/5, Ushiba)
  * --(IM アクチュエータ V1)-- (2018/4/5, Ushiba)
  * --(IM アクチュエータ V2)-- (2018/4/5, Ushiba)
  * --(IM アクチュエータ V3)-- (2018/4/5, Ushiba)
  * IM アクチュエータ H1 (2018/X/XX, Ushiba)
  * IM アクチュエータ H2 (2018/X/XX, Ushiba)
  * IM アクチュエータ H3 (2018/X/XX, Ushiba)
  * IM アクチュエータ V1 (2018/X/XX, Ushiba)
  * IM アクチュエータ V2 (2018/X/XX, Ushiba)
  * IM アクチュエータ V3 (2018/X/XX, Ushiba)
Line 203: Line 184:
  * --(MN アクチュエータ H1)-- (2018/4/5, Ushiba)
  * --(MN アクチュエータ H2)-- (2018/4/5, Ushiba)
  * --(MN アクチュエータ H3)-- (2018/4/5, Ushiba)
  * --(MN アクチュエータ V1)-- (2018/4/5, Ushiba)
  * --(MN アクチュエータ V2)-- (2018/4/5, Ushiba)
  * --(MN アクチュエータ V3)-- (2018/4/5, Ushiba)
  * MN アクチュエータ H1 (2018/X/XX, Ushiba)
  * MN アクチュエータ H2 (2018/X/XX, Ushiba)
  * MN アクチュエータ H3 (2018/X/XX, Ushiba)
  * MN アクチュエータ V1 (2018/X/XX, Ushiba)
  * MN アクチュエータ V2 (2018/X/XX, Ushiba)
  * MN アクチュエータ V3 (2018/X/XX, Ushiba)
Line 210: Line 191:
  * SBS ダンピングコイル(V1-V4) (2018/X/XX, Ushiba, Tomaru) 今回は無し   * SBS ダンピングコイル(V1-V4) (2018/X/XX, Ushiba, Tomaru)
Line 212: Line 193:
  * --(MN moving mass1)-- (2018/4/5, Ushiba)
  * --(MN moving mass2)-- (2018/4/5, Ushiba)
  * --(PF moving mass1)-- (2018/4/5, Ushiba)
  * --(PF moving mass2)-- (2018/4/5, Ushiba)

 * ダンピング制御
  * MN, BFを用いたヒエラリカル制御 (201
8/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
  * MN moving mass1 (2018/8/XX, Ushiba)
  * MN moving mass2 (2018/8/XX, Ushiba)
  * PF moving mass1 (2018/8/XX, Ushiba)
  * PF moving mass2 (2018/8/XX, Ushiba)

Check list for ITMX vacuum in Summer of 2018

  • Term: ~2018/9

Schedule

  • 2018/8/16(Thur) 12:30 meeting at fan hut.
  • 2018/8/20の週: アルミホイルを外す。鏡の測定の位置確認、WABの設定。
  • 2018/8/21: IPリリース、調整
  • 2018/8/27(Mon) : Closing IXC、同日cryostatの掃除をする。
  • 2018/8/30(Wed) : Closing IXA by Mira-Pro
  • 2018/8/30(Thur)夕方- : pump down、30日にポンプ一台で粗挽き、31日金曜日に本引き
  • 2018/9/3-5: leak check
  • 2018/9/5-7: φ800のフランジ開け
  • 9/10: 停電対策で真空関係の対応


Each item should have following format;

  • item (checked date, checked person)

Once the item has been checked, it will be like:

  • item (2018/8/20, Somebody)


Preparation of monitors during pump down

  • Tcam for ITMX (2018/8/?? Yokozawa) -> (2018/8/22 planed)

  • Vacuum gage for KAGRA (2018/8/XX Tomaru) -> (2018/8/XX planed)

  • 真空槽の傾きをdial gaugeで測る。 (2018/8/XX Kimura) -> (2018/8/27~ planed, measured from 8/30~)

  • ITMX 機器制御 for status monitors (2018/8/XX Tomaru) -> (2018/8/XX planed)

  • Vacuum gauge monitor at the control room (2018/8/XX Tomaru) -> (2018/8/XX planed)

真空引き後、追加項目

  • 真空引き後、防振系の動作チェック (2018/X/XX, Fujii) -> (2018/8/XX planed)

  • Xarmコミッショニング時、IXA ゲードバルブの動作チェック (2018/X/XX, Kimura) -> (2018/9/XX planed)

  • Xarmコミッショニング時、BS ゲードバルブの動作チェック (2018/X/XX, Kimura) -> (2018/9/XX planed)

Type-A tower (高橋)

  • IPリリース、調整 (2018/X/XX, Okutomi) -> (2018/8/21 planed)

  • Fishing rodの動作チェック (2018/X/XX, Takahashi)
  • Tuning of BF (2018/X/XX, Takahashi)
  • Tuning of F3 (2018/X/XX, Takahashi)
  • Tuning of TF (2018/X/XX, Takahashi)
  • Tuning of position of BF damper (2018/X/XX, Takahashi)
  • Centering IP (2018/X/XX, Takahashi)
  • BF yaw picomotorの動作確認 (2018/X/XX, Takahashi)
  • トップ真空槽蓋閉め (2018/X/XX, Takahashi) -> (2018/8/30 planed by Mira-pro)

  • トップ真空槽ボルト閉め (2018/X/XX, Takahashi) -> (2018/8/30 planed by Mira-pro)

  • クロス菅ボルト閉め (2018/X/XX, Takahashi) -> (2018/8/30 planed by Mira-pro)

  • IPの制御 (2018/X/XX, Takahashi)
  • BFのdamping制御 (2018/X/XX, Okutomi) -> (2018/X/XX planed)

  • BF FRによるmirrorの高さ調整 (2018/X/XX, Takahashi) -> (2018/8/?? planed)

  • BF yaw picomotorによるmirrorのyaw調整 (2018/X/XX, Ushiba) -> (2018/8/?? planed)

  • 事前にTypeA、Cryopayloadのアラインメント機構が動くかどうか確認する。 (2018/X/XX, Ushiba)
  • BF温度計つなぎこみ (2018/X/XX, Takahashi, Ushiba) -> (2018/8/?? planed)

鏡板閉止 (Kimura)

  • 8K および 80Kシールドにつける窓類の取り付け (2018/X/XX Kimura) -> (2018/8/27,28 planed)

  • 輻射シールドのシャッター開確認 (2018/X/XX Kimura) -> (2018/8/27,28 planed)

  • 当該部のSuper Insulation(SI)取り外し確認 (2018/X/XX Kimura) -> (2018/8/27,28 planed)

  • 鏡板取付前の変換フランジ取付 (2018/8/10 Kimura)

  • 鏡板取付後のビューポート取付 (2018/X/XX, Ushiba) -> (2018/8/27,28 planed)

  • Oplev用の島取付 (2018/X/XX, Ushiba) -> (2018/8/27,28 planed)

  • Q massの取り付け (2018/X/XX Kimura) -> (2018/8/27-31 planed)

IXV支持構造体のセット確認

  1. コーンベローズ脚ロックナットの固定確認 3箇所 (但し、手締め)(2018/X/XX, Kimura) -> (2018/8/30 planed)

  2. チェンバー本体用 3箇所 <- 今回は固定のまま (2018/X/XX, Kimura) -> (2018/8/30 planed)

WAB (阿久津)at IXC

  • Type-A+cryopayloadがbalance地点に調整されしだい、finalize(2018/X/XX, Akutsu)-> (2018/8/22、23)

    • finalize前に、
      • Type-A+cryopayloadがbalance地点に調整されているか
      • Assembly frameが動く状態になっているか
    • やる作業としては
      • WABを定位置に固定、WABにヒートリンクなどを取り付ける
  • cooling bar1本設置 (2018/X/XX, Tomaru) -> (2018/8/27 planed)

  • Cooling barからHeat link取り付け (2018/X/XX, Tomaru) -> (2018/8/27 planed)

NAB(阿久津)at IXA

  • NABがリリースされているか?(2018/08/09, Akutsu)

  • NAB/Tcam frameについている白テープを全て剥がしたか? (Yokozawa、Akutsu) -> (2018/8/20 planed)

  • NABのQ-factor測定の状況は確認したか (2018/08/XX, Akutsu) -> (2018/8/20-29 planed)

真空引き開始前後 (木村)

  1. 真空フランジを開放し、再度閉止した箇所の確認(リーク試験箇所の確定に必要な情報です。)
    • グループ毎の申告による
      • IXA Top閉止 (2018/X/XX, Kimura) -> (2018/8/30 planed)

      • IXA 鏡板閉止 (2018/X/XX, Kimura) -> (2018/8/30 planed)

      • IXV top flange: VIS group (2018/X/XX, Kimura) -> (2018/8/30 planed)

      • クロス菅鏡板2箇所: CRY group, VIS group (2018/X/XX Kimura) -> (2018/8/30 planed)

      • ICF152送風機接続ポート(空気導入用ポート取り付け): CRY group (2018/X/XX Kimura) -> (2018/8/30 planed)

      • IXC鏡板箇所: CRY group (2018/X/XX Kimura) -> (2018/8/27、28 planed)

      • IXC 鏡板ViewPort 用変換フランジ1箇所:CRY group (2018/8/10, Kimura)

      • IXC ViewPort 3箇所(鏡板1箇所、容器2箇所): AOS (2018/X/XX, Ushiba) -> (2018/8/28 planed)

      • 冷凍機NW-50フランジ交換 3箇所: CRY group (2018/6, Kimura)

      • IXA ICF152 2箇所: cal group (2018/X/XX, Yokozawa, 要確認)
      • IXC~クロス管挿しフランジ取り外しとフランジ再締結 (2018/6, Kimura)

      • IXA~IXC間レーザーハザード用挿しフランジ取り外しとフランジ再締結 (2018/3/12, Kimura)

      • IXAのIXC側ベローズ締結部(寺田さん、内山さんによるビーム位置測定で使用) (2018/3/12, Kimura)

      • IXAの上ぶた (NAB/TCam/BafflePDs)

      • IXAの両サイドフランジ (NAB/TCam/BafflePDs)

      • IXAのICF70 viewport。3km腕側で、-Y側。 (NAB) (2018/6, Akutsu)

      • IXAの上側のICF203部分。コネクタつきのフランジに交換した (BafflePD) (2018/8/7, Enomoto)

  2. 真空引き
    1. 真空計2台 ON (2018/X/XX, Kimura)
    2. 粗挽きポンプスタート (2018/X/XX, Kimura)
    3. 大まかなリークチェック (2018/X/XX, Kimura)
    4. ターボポンプ冷却水循環装置スタート (2018/X/XX, Kimura)
    5. ターボポンプスタート (2018/X/XX, Kimura)
  3. リーク試験 (2018/X/XX, Kimura)
    • (リーク判定 < 1x10-10 Pa・m3/s)

  4. ゲートバルブ動作試験 (2018/8/XX, Kimura) <- 今回は無し

  5. (温度・圧縮機のモニター) <- 今回は無し

    • スタートさせる (2018/XX/XX, 都丸、麻生) -> (2018/X/XX planed)

    • 温度・圧縮機のループテスト (2018/XX/XX, 都丸、麻生、木村) -> 冷却開始前までに予定

Cryo payload (都丸、牛場)

  • Cryo payload EQ stopの隙間のチェック5mm程度 (2018/X/XX, Ushiba)
  • センサーチェック
    • TM OpLev Pitch (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)

    • TM OpLev Yaw (2018/X/XX, Ushiba, Tomaru)

    • TM OpLev Length (2018/X/XX, Ushiba, Tomaru)

    • IM PS H1 (2018/X/XX, Ushiba) -> (2018/X/XX planed)

    • IM PS H2 (2018/X/XX, Ushiba)
    • IM PS H3 (2018/X/XX, Ushiba)
    • IM PS V1 (2018/X/XX, Ushiba)
    • IM PS V2 (2018/X/XX, Ushiba)
    • IM PS V3 (2018/X/XX, Ushiba)
    • MN PS H1 (2018/X/XX, Ushiba)
    • MN PS H2 (2018/X/XX, Ushiba)
    • MN PS H3 (2018/X/XX, Ushiba)
    • MN PS V1 (2018/X/XX, Ushiba)
    • MN PS V2 (2018/X/XX, Ushiba)
    • MN PS V3 (2018/X/XX, Ushiba)
    • MN OpLev Pitch (2018/X/XX, Miyamoto) -> (2018/X/XX planed)

    • MN OpLev Yaw (2018/X/XX, Miyamoto)

    • 温度計A (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)

    • 温度計B (2018/X/XX, Ushiba, Tomaru)
    • 温度計C (2018/X/XX, Ushiba, Tomaru)
    • 温度計D (2018/X/XX, Ushiba, Tomaru)
    • 温度計E (2018/X/XX, Ushiba, Tomaru)
    • 温度計F (2018/X/XX, Ushiba, Tomaru)
    • 温度計G (2018/X/XX, Ushiba, Tomaru)
    • 温度計H (2018/X/XX, Ushiba, Tomaru)
  • アクチュエータチェック
    • TM アクチュエータ H1 (2018/X/XX, Ushiba) -> (2018/X/XX planed)

    • TM アクチュエータ H2 (2018/X/XX, Ushiba)
    • TM アクチュエータ H3 (2018/X/XX, Ushiba)
    • TM アクチュエータ H4 (2018/X/XX, Ushiba)
    • IM アクチュエータ H1 (2018/X/XX, Ushiba)
    • IM アクチュエータ H2 (2018/X/XX, Ushiba)
    • IM アクチュエータ H3 (2018/X/XX, Ushiba)
    • IM アクチュエータ V1 (2018/X/XX, Ushiba)
    • IM アクチュエータ V2 (2018/X/XX, Ushiba)
    • IM アクチュエータ V3 (2018/X/XX, Ushiba)
    • MN アクチュエータ H1 (2018/X/XX, Ushiba)
    • MN アクチュエータ H2 (2018/X/XX, Ushiba)
    • MN アクチュエータ H3 (2018/X/XX, Ushiba)
    • MN アクチュエータ V1 (2018/X/XX, Ushiba)
    • MN アクチュエータ V2 (2018/X/XX, Ushiba)
    • MN アクチュエータ V3 (2018/X/XX, Ushiba)
    • SBS ダンピングコイル(V1-V4) (2018/X/XX, Ushiba, Tomaru)
    • MN moving mass1 (2018/8/XX, Ushiba)
    • MN moving mass2 (2018/8/XX, Ushiba)
    • PF moving mass1 (2018/8/XX, Ushiba)
    • PF moving mass2 (2018/8/XX, Ushiba)

KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX (last edited 2018-10-09 10:39:24 by OsamuMiyakawa)